Data-center permit refusal affirmed September 9; court challenge reported, with construction approval and operating capacity unverified.
Published and sources reviewed November 14, 2026.
Compare · Track milestones · FJI evidence
Investment takeaway
The proposed conversion illustrates the financial risk between preparatory spending and an enforceable right to build. The administrative appeal failed, while the developer’s vested-rights arguments remain distinct from a court judgment. No project return, secured power or funded construction is established.
Project at a Glance
- Location
- 3600 and 3455 International Park Drive, DeKalb County, Georgia
- Project stage
- Proposed / development
- Capacity scope
- 651 MW requested from Georgia Power, according to developer counsel; secured service and operating IT MW unverified.
- Named companies
- Shadowbox Studios; Henrico 183, LLC; Georgia Power (requested service only)
FJI source-qualified: four-document gate met, including project-specific government evidence. Qualification evidence and decisions →
The Permit Dispute
The project concerns a proposed data-center conversion on International Park Drive, rather than a confirmed operating data center. The official appeal record names both Shadowbox and Henrico 183. Counsel and independent hearing reporting connect that appeal to the permit refusal; the minutes alone do not describe the proposed use.
Sources and Claim Boundaries
Final September 9 minutes name Shadowbox Studios and Henrico 183, LLC in case A-26-1248202, parcel 15 051 01 001, at 3600 and 3455 International Park Drive. The board affirmed the administrative decision 5–0–0. The minutes record the appeal and result but do not themselves identify the proposed use as a data center. DeKalb County Zoning Board of Appeals →
Shadowbox’s counsel identifies the affirmed decision as refusal of a data-center land-development permit. Its September 18 account says the company requested 651 MW from Georgia Power and spent more than $30 million pursuing the conversion. Those are interested-party statements, not verified power service, operating IT load or audited spending. Counsel argues vested rights and challenges the moratorium; those legal positions are not court findings. Bloom Parham, counsel for Shadowbox →
September 9 hearing reporting independently identifies the appeal as Shadowbox’s data-center proposal and reports that the board affirmed the denial. The county’s position was that earlier planning letters were not legally binding. The article attributes a $37 million preparation figure to the studio’s lawyers, differing from counsel’s later more-than-$30-million description; neither figure is adopted as independently verified spending. Atlanta News First →
August 13 reporting describes Shadowbox and Henrico 183’s August 5 Superior Court lawsuit seeking invalidation of the moratorium, permission to develop and compensation. It reports a film-studio land-disturbance permit issued in 2022, followed by a proposed conversion to data-center use. The county declined to comment on pending litigation. The earlier studio permit is not a data-center construction approval. WABE / Decaturish →
Next Evidence
Retrieve the current DeKalb Superior Court docket and any order on the moratorium or vested-rights claims; verify a subsequent issued permit and utility service agreement before changing delivery status.
Research Limits
Current court docket and any later judgment, issued data-center permits, secured electricity, actual spending, financing, end user and site-specific operating IT load remain unresolved.
The proposal is contested, not shown cancelled. No updated court disposition was verified in this review. AI-assisted public-source research; no interviews, private financing review or independent site measurement.
Related Georgia Analysis
Georgia’s Data Center Promises Face Different Delivery Tests compares power, public-benefit and delivery evidence.
Related project records: OpenAI Project Camellia · Google LaGrange / PRL2 · Google Columbia County.
Company investor information & quarterly statements
Financial-disclosure review remains incomplete for one or more participants. The company-level limitations below remain unresolved; this section does not establish full corporate-disclosure verification.
Corporate disclosures provide company-wide context. They do not establish this project’s revenue, spending, profit, ownership share or operating capacity. Disclosure verification records →