Project directory / Georgia
OpenAI Project Camellia
Power-service contract approved; site-plan decision deferred to November 17, with construction approvals and operating capacity unresolved.
Published and sources reviewed November 11, 2026.
Compare · Track milestones · FJI evidence
Investment takeaway
The material investment question is whether phased utility commitments and local approvals become funded, buildable capacity. The county’s $20 billion announcement is not a spending total. Community benefits, taxes and digital-service credits have different scopes and are not additive project capital.
Project at a Glance
- Location
- Effingham County / Rincon, Georgia
- Project stage
- Proposed / development
- Capacity scope
- 3.2 GW planned phased utility power, 2028–2032; accepted IT MW unverified.
- Named companies
- OpenAI; Octans GA LLC; Georgia Power
FJI source-qualified: four-document gate met, including project-specific government evidence. Qualification evidence and decisions →
Research Update · November 14, 2026
Power-service contract approved; site-plan decision deferred to November 17, with construction approvals and operating capacity unresolved.
Georgia Power announced regulatory approval of its OpenAI contract on August 26. It describes 3,200 MW of new demand, OpenAI paying required infrastructure costs and up to 1,000 MW of flexible demand response. The utility’s projected customer savings cover a broader large-load portfolio, not Camellia alone. Georgia Power →
The PSC’s September fact sheet describes the August 26 review of a 3,200 MW contract and an agreement not to recover early-termination incremental costs from residential and small-business customers during the unfulfilled contract term. It also describes a generation-cost backstop through 2031 and twice-yearly public operational and financial reports on data-center customers. These are specified protections, not proof of energized project capacity. Georgia Public Service Commission →
The official meeting listing has a tentative November 17 regular meeting at 5 p.m. and work session at 4 p.m. Eastern. Independent reporting says the Camellia site-plan decision was deferred to that date; this refresh verified the meeting listing, but could not retrieve the new agenda body or confirm a future vote outcome. Effingham County meeting calendar →
WTOC reports the November 3 site-plan decision was postponed to November 17 after questions about noise buffers and wetlands. Deferral does not constitute rejection or cancellation. WTOC →
Next Evidence
Check the November 17 county proceedings and actual site-plan disposition, then phase permits, financing, power delivery and customer acceptance.
Targeted source review November 14, 2026. Earlier dated observations below retain their original scope. This update does not establish full FJI certification.
Research Update · November 11, 2026
Site-plan decision deferred to November 17, according to November reporting; construction approvals and operating capacity unverified.
The July 22 county announcement describes a $20 billion proposed investment and 400 long-term jobs at Savannah Gateway Industrial Hub. These are announced investment and employment expectations, not paid capital or jobs independently counted. Effingham County →
OpenAI describes 3.2 GW of power delivered in phases during 2028–2032, an $80 million community-benefit commitment and future public independent audits. Financing, design, phasing and operating model remain development work; power is not energized IT load. OpenAI →
Staff report for Site-26-6 and Site-26-10 identifies Octans GA LLC as parcel owner and approximately 1,347 acres across parcels 433-1E and 433-1. A staff report and preliminary layout do not establish an issued construction approval. Effingham County planning staff →
The Herald reports commissioners deferred the November 3 site-plan decision until November 17 over noise-protection questions. The preliminary layout has six data-center buildings. This is a deferred decision, not rejection or cancellation. Effingham Herald →
Georgia Power names OpenAI as the customer and describes long-term service and financial protections. The public announcement does not disclose the full tariff, security package or energized capacity. Georgia Power →
County guidance says the review is incomplete. Its current plan describes no diesel backup after completion and a sequence of permits and inspections. Earlier descriptions and life-safety generators require reconciliation; no blanket generator-free claim is made. Effingham County resource center →
Next Evidence
November 17 site-plan reconsideration; final approvals, phase power terms, financing and customer acceptance.
Source review November 11, 2026. Forecasts remain attributed; absent measurements remain unknown. This update does not claim full FJI certification.
Research Limits
Current accepted IT MW, actual spending, executed financing, precise phase boundaries, utility contract economics, ownership/disclosure completeness and site-level returns remain unresolved.
Planned power is not operating IT load. Announced investment is not spent capital. AI-assisted public-source research; no private contract review or independent site measurement.
Related Georgia Analysis
Georgia’s Data Center Promises Face Different Delivery Tests compares the power, public-benefit and delivery evidence across these developments.
Related project records: Google LaGrange / PRL2 · Google Columbia County
Company investor information & quarterly statements
Financial-disclosure review remains incomplete for one or more participants. The company-level limitations below remain unresolved; this section does not establish full corporate-disclosure verification.
Corporate disclosures provide company-wide context. They do not establish this project’s revenue, spending, profit, ownership share or operating capacity. Disclosure verification records →