Project directory / Georgia
Google LaGrange / PRL2
First-building construction reported; PRL2 expansion and community commitments remain separate from commissioning evidence.
Published and sources reviewed November 11, 2026.
Compare · Track milestones · FJI evidence
Investment takeaway
LaGrange’s municipal utility expects future demand to support city finances, but its budget is a forecast. PRL2’s $1 billion estimate and 350 MW connected-load filing describe a planned phase, not paid capital or operating IT capacity. Historical developer targets should not replace current Google disclosures.
Project at a Glance
- Location
- 411 Pegasus Parkway, LaGrange, Troup County, Georgia
- Project stage
- Under construction
- Capacity scope
- 350 MW estimated peak connected load in PRL2 filing; current operating IT MW unverified.
- Named companies
- Google / Alphabet; KDC; MEAG; City of LaGrange
FJI source-qualified: four-document gate met, including project-specific government evidence. Qualification evidence and decisions →
Research Update · November 14, 2026
First-building construction reported; PRL2 expansion and community commitments remain separate from commissioning evidence.
Google continues to identify LaGrange and Columbia County as separate 2026 new developments. Its state-level economic-impact figures do not establish spending or operating capacity at either campus. Google →
Groundswell’s May 4 announcement identifies $1 million of Google support for its LaGrange SOUL home-repair and energy-efficiency program, expected to support at least 50 income-qualified households. This is a community-program commitment, not campus capital expenditure, a utility tariff or proof that the newly funded homes have been completed. Groundswell →
DCD’s July 27 report identifies work on the first building and a proposed approximately 470,000-square-foot second building at 411 Pegasus Parkway, with a $1 billion estimate and a 2029 target. It says further phases are speculative and Thor Equities is no longer involved. No new commissioning confirmation was found in this refresh. Data Center Dynamics →
Next Evidence
Verify first-phase commissioning against the city’s Q2 2027 budget forecast; retrieve current PRL2 permits, phase-specific power and SOUL program delivery.
Targeted source review November 14, 2026. Earlier dated observations below retain their original scope. This update does not establish full FJI certification.
Research Update · November 11, 2026
First-building construction reported; subsequent PRL2 regional review completed, with separate phase permits and commissioning unverified.
Google separately identifies LaGrange as a 2026 development, distinct from Douglas County and Columbia County. Google →
PRL2 at 411 Pegasus Parkway includes an existing data-center building and a proposed approximately 470,000-square-foot subsequent building. KDC acts for the owner. The phase targets 2029; later phases remain speculative. Georgia DCA DRI 4797 initial form →
The filing estimates $1 billion build-out value and 350 MW peak connected electrical load, naming MEAG for energy and the City of LaGrange for water/sewer. Planning demand is 2–4 MGD water and 0.2–0.6 MGD wastewater, not measured use. Georgia DCA DRI 4797 additional form →
The city budget anticipates operations ramping over five years beginning Q2 2027. Projected full-build utility margins are municipal forecasts, not Google earnings or proof of current operation. City of LaGrange FY2027 budget →
July 27 reporting describes first-building work and the PRL2 expansion. Thor Equities told DCD it is no longer involved; its older 50 MW/400 MW and late-2026/early-2027 figures must not be treated as current Google operating guidance. Data Center Dynamics →
Regional review is marked completed, with an August 12 finding. Regional review is not a building permit, occupancy certificate or service acceptance. Georgia DCA DRI 4797 summary →
Next Evidence
Verify first-phase commissioning against the city’s Q2 2027 ramp forecast, plus PRL2 building permits and phase-specific power.
Source review November 11, 2026. Forecasts remain attributed; absent measurements remain unknown. This update does not claim full FJI certification.
Research Limits
Current accepted IT MW, actual spending, executed financing, precise phase boundaries, utility contract economics, ownership/disclosure completeness and site-level returns remain unresolved.
Planned power is not operating IT load. Announced investment is not spent capital. AI-assisted public-source research; no private contract review or independent site measurement.
Related Georgia Analysis
Georgia’s Data Center Promises Face Different Delivery Tests compares the power, public-benefit and delivery evidence across these developments.
Related project records: OpenAI Project Camellia · Google Columbia County
Company investor information & quarterly statements
Financial-disclosure review remains incomplete for one or more participants. The company-level limitations below remain unresolved; this section does not establish full corporate-disclosure verification.
Corporate disclosures provide company-wide context. They do not establish this project’s revenue, spending, profit, ownership share or operating capacity. Disclosure verification records →