Georgia · Under construction

Google LaGrange / PRL2

First-building construction reported; PRL2 expansion and community commitments remain separate from commissioning evidence.

Published and sources reviewed November 11, 2026.

Compare · Track milestones · FJI evidence

Investment takeaway

LaGrange’s municipal utility expects future demand to support city finances, but its budget is a forecast. PRL2’s $1 billion estimate and 350 MW connected-load filing describe a planned phase, not paid capital or operating IT capacity. Historical developer targets should not replace current Google disclosures.

Project at a Glance

Location
411 Pegasus Parkway, LaGrange, Troup County, Georgia
Project stage
Under construction
Capacity scope
350 MW estimated peak connected load in PRL2 filing; current operating IT MW unverified.
Named companies
Google / Alphabet; KDC; MEAG; City of LaGrange

FJI source-qualified: four-document gate met, including project-specific government evidence. Qualification evidence and decisions →

Research Update · November 14, 2026

First-building construction reported; PRL2 expansion and community commitments remain separate from commissioning evidence.

Google continues to identify LaGrange and Columbia County as separate 2026 new developments. Its state-level economic-impact figures do not establish spending or operating capacity at either campus. Google →

Groundswell’s May 4 announcement identifies $1 million of Google support for its LaGrange SOUL home-repair and energy-efficiency program, expected to support at least 50 income-qualified households. This is a community-program commitment, not campus capital expenditure, a utility tariff or proof that the newly funded homes have been completed. Groundswell →

DCD’s July 27 report identifies work on the first building and a proposed approximately 470,000-square-foot second building at 411 Pegasus Parkway, with a $1 billion estimate and a 2029 target. It says further phases are speculative and Thor Equities is no longer involved. No new commissioning confirmation was found in this refresh. Data Center Dynamics →

Next Evidence

Verify first-phase commissioning against the city’s Q2 2027 budget forecast; retrieve current PRL2 permits, phase-specific power and SOUL program delivery.

Targeted source review November 14, 2026. Earlier dated observations below retain their original scope. This update does not establish full FJI certification.

Research Update · November 11, 2026

First-building construction reported; subsequent PRL2 regional review completed, with separate phase permits and commissioning unverified.

Google separately identifies LaGrange as a 2026 development, distinct from Douglas County and Columbia County. Google →

PRL2 at 411 Pegasus Parkway includes an existing data-center building and a proposed approximately 470,000-square-foot subsequent building. KDC acts for the owner. The phase targets 2029; later phases remain speculative. Georgia DCA DRI 4797 initial form →

The filing estimates $1 billion build-out value and 350 MW peak connected electrical load, naming MEAG for energy and the City of LaGrange for water/sewer. Planning demand is 2–4 MGD water and 0.2–0.6 MGD wastewater, not measured use. Georgia DCA DRI 4797 additional form →

The city budget anticipates operations ramping over five years beginning Q2 2027. Projected full-build utility margins are municipal forecasts, not Google earnings or proof of current operation. City of LaGrange FY2027 budget →

July 27 reporting describes first-building work and the PRL2 expansion. Thor Equities told DCD it is no longer involved; its older 50 MW/400 MW and late-2026/early-2027 figures must not be treated as current Google operating guidance. Data Center Dynamics →

Regional review is marked completed, with an August 12 finding. Regional review is not a building permit, occupancy certificate or service acceptance. Georgia DCA DRI 4797 summary →

Next Evidence

Verify first-phase commissioning against the city’s Q2 2027 ramp forecast, plus PRL2 building permits and phase-specific power.

Source review November 11, 2026. Forecasts remain attributed; absent measurements remain unknown. This update does not claim full FJI certification.

Research Limits

Current accepted IT MW, actual spending, executed financing, precise phase boundaries, utility contract economics, ownership/disclosure completeness and site-level returns remain unresolved.

Planned power is not operating IT load. Announced investment is not spent capital. AI-assisted public-source research; no private contract review or independent site measurement.

Related Georgia Analysis

Georgia’s Data Center Promises Face Different Delivery Tests compares the power, public-benefit and delivery evidence across these developments.

Related project records: OpenAI Project Camellia · Google Columbia County

Company investor information & quarterly statements

Financial-disclosure review remains incomplete for one or more participants. The company-level limitations below remain unresolved; this section does not establish full corporate-disclosure verification.

Corporate disclosures provide company-wide context. They do not establish this project’s revenue, spending, profit, ownership share or operating capacity. Disclosure verification records →