Intel Mission Campus / Santa Clara enterprise data centers
FJI source-qualified: four-document gate met, including project-specific government evidence. Qualification evidence and decisions →
Project status: Existing enterprise computing documented; incremental Juliette power allocation authorized and pending. Capacity scope: Existing 62 MVA utility allocation; planned +17 to 79 MVA no earlier than August 1, 2029; MVA is not IT MW. How we verify evidence.
Compare this project → · Track its catalysts →
← Back to project index- Location
- United States / California / Santa Clara — representative locality pin
- Readiness
- Operating
- Status
- Existing enterprise computing documented; incremental Juliette power allocation authorized and pending
- Capacity & scope
- Existing 62 MVA utility allocation; planned +17 to 79 MVA no earlier than August 1, 2029; MVA is not IT MW
- Named companies
- Intel; Silicon Valley Power / City of Santa Clara
- Next milestone
- Executed agreement, transformer works and conditional incremental power acceptance
- Reviewed
- October 8, 2026
Phase-specific evidence; approximate locality pin. Reviewed October 8, 2026.
The investment takeaway
Intel has genuine enterprise computing campuses. This first Intel-owned inventory entry diversifies coverage beyond cloud landlords and proposed AI megasites. Its evidence establishes internal computing and a specific power expansion, while the incremental allocation is conditional and undelivered.
One campus, not two buildings
DCD’s original 2019 tour describes D2P3/D2P4 within a converted fab alongside Intel headquarters, serving enterprise IT and chip-design workloads. Intel’s campus page corroborates their identity. The two internal facilities count as one campus at 3750 Juliette Lane; their historical capacities are not newly verified operating load.
Government authorization and power scope
Santa Clara File 25-80 records May 27, 2025 consent approval authorizing the city manager to execute an agreement. The report documents ongoing data-center expansion and existing 62 MVA allocation. Additional 17 MVA reaches 79 MVA no earlier than August 1, 2029, subject to grid expansion and other terms. MVA is apparent-power allocation and cannot be relabeled operating IT MW.
Capital obligations and utility ownership
Intel must pay substation design, procurement, construction, inspection and testing costs, procure the third transformer and pay load-development fees, currently estimated around $10 million. City/SVP handles installation and retains ownership/operation. This official structure is stronger than a generic power pledge, but authorization does not establish execution, procurement or completion.
Historical technology evidence
Intel’s July 2021 fuel-cell white paper describes Santa Clara pilots, including a 2018 5 MW installation. Company-reported resilience and older recycled-water/cooling statistics remain historical. No current Bloom supplier award, GPU fleet or commercial AI tenant is inferred. Intel page build dates do not refresh underlying performance claims.
Risks, catalysts and held second campus
Grid-expansion dependencies, transformer timing and internal capital priorities affect added power. Executed terms, works and delivered allocation would improve expansion confidence. A second Jones Farm/Hillsboro entry is held because precise government evidence for the actual computing facility was insufficient; the separate announced $700 million lab was canceled. Semiconductor fabs and support buildings are not data-center additions.
Financial significance
Intel funds substation expansion and an estimated $10 million load-development fee, separate from unspecified construction costs. Our analysis: this supports internal engineering infrastructure and utility capital requirements, not externally leased hyperscale revenue. No site-level INTC earnings, GPU contract or return model is established. Funding obligations are not verified actual expenditure.
Sources and claim verification
Structured source and government-record audit → · Reviewed October 8, 2026. Event dates and publication dates are separate.
Distinct project-specific documents; repeated releases count once. Company claims remain attributed and do not independently establish delivery.
- City of Santa Clara · 2025-05-27 · reviewed 2026-10-08 · event 2025-05-27
File 25-80, created January 7: consent approval May 27 authorizes manager to execute Juliette substation agreement. Existing 62 MVA allocation; planned 17 MVA addition to 79 MVA no earlier than August 1, 2029, conditional on System Expansion Plan and other terms. Intel funds all substation costs plus estimated $10 million load-development fee; SVP owns/operates infrastructure. Authorization does not prove execution or completion.
Government record → - DatacenterDynamics / Sebastian Moss · 2025-06-04 · reviewed 2026-10-08
Specialist reporting describes utility expansion economics. Its approval-pending wording is superseded by the city’s recorded May 27 vote; neither story proves construction or energization.
Independent specialist reporting → - DatacenterDynamics / Sebastian Moss · 2019-03-13 · reviewed 2026-10-08
Original site visit/interviews document operating converted D2 fab and enterprise/chip-design computing. Historical 31 MW D2P3 and 5 MW D2P4 capacities are 2019 reported figures, not verified current load or separate campuses.
Independent specialist reporting → - Intel IT · 2021-07 · reviewed 2026-10-08
Operator white paper describes Santa Clara fuel-cell pilots including 2018 5 MW installation and later configurations. Historical company resilience claims do not establish current fleet, supplier contracts or Bangalore deployment at this campus.
Company disclosure → - Intel Explore Mission Campus · publication date not established · reviewed 2026-10-08
Primary campus page identifies D2P3/D2P4 and historical recycled-water/cooling practices. Metrics date to 2013–17; site build footer is not evidence of refreshed performance or current readiness.
Company disclosure →
Company investor information & quarterly statements
Corporate-disclosure certification held: Silicon Valley Power: held; Research packet retains a corporate disclosure hold.
Intel
Owner/operator internalcomputing consumer
Official investor & shareholder information · Quarterly financial statements: Q2 2026 ended June27 2026
Silicon Valley Power
Municipalutility
Disclosure verification held: Official investor and quarterly document coverage remains incomplete.
Private participant: Government,cooperative,academic,or nonlisted operatingcounterparty: no public quarterlystatement requirement assumed; applicable annual/interimreporting and entity structure need explicit documented exception.
Corporate disclosures provide company-wide context. They do not establish this project’s revenue, spending, profit, ownership share or operating capacity. Disclosure verification records →