QTS Cambois / Blyth AI campus
FJI source-qualified: four-document gate met, including project-specific government evidence. Qualification evidence and decisions →
Published and scoped evidence reviewed October 16, 2026. Historical source events retain their own dates.
QTS / Blackstone-affiliated funds research · FJI evidence · Compare · Milestones · European coverage
Project at a glance
- Location
- Former Blyth Power Station site, Cambois, Northumberland, United Kingdom
- Status
- Enabling earthworks documented; first-building delivery remains a future milestone
- Capacity scope
- 720 MW marketed full-campus figure; 1.1 GW separately reported power scope unresolved; neither is current IT load.
- Business model
- Phased hyperscale cloud and AI-supporting infrastructure
- Next milestone
- Verify first-building construction and commissioned service; reconcile 720 MW marketed capacity with reported 1.1 GW power scope.
Representative locality-area pin, not a surveyed campus boundary or entrance.
Physical and legal scope
This is the Cambois former-power-station redevelopment near Blyth. It is separate from the smaller West Sleekburn proposal described in local reporting.
Capacity and capital boundaries
The projected GBP10 billion investment is not a financing close or cash spent. The marketed 720 MW and separately reported 1.1 GW power figure have unresolved boundaries; neither enters delivered-IT totals.
Progress toward operation
fDi reports enabling works from October 2025 using planning and environmental-permit reporting. QTS describes continued earthworks in 2026 and future first-building construction. Enabling work is classified as construction here, with the building phase kept explicit.
Investor read-through
Our analysis: early earthworks and an accelerated phasing proposal improve visibility into the development process, while rent/service commencement remains ahead. Fund ownership does not establish listed-company project earnings.
Delivery commitments and dated checkpoints
Target: fDi reports first-pair operations targeted for 2029 and four buildings by 2030; these are proposed schedules.
- 2024-09-25: The UK announces a projected GBP10 billion Blackstone-backed AI data-centre investment at Blyth. This is a planned commitment, not cash spent. Original project-specific government investment announcement
- Undated current source: QTS identifies its Cambois campus and continuing earthworks in 2026, with first-building construction planned. Its older FAQ schedule is retained as historical wording. Original company project update
- Undated current source: The account identifies QTS as developer/operator and describes ten buildings with a marketed 720 MW total; it does not certify delivered power or precise IT/facility boundary. Regional investment-promotion project account
- 2026-05-18: fDi reports enabling works from October 2025 and proposed operations in 2029 for the first pair, with four buildings targeted by 2030. Its cited 1.1 GW full-project power figure is not treated as equivalent to the marketed 720 MW. Independent reporting using planning documents, FOI and company comment
- 2026-06-08: Place North East describes applications for remaining enabling works, separately from existing approvals and future building delivery. Independent local planning reporting
- 2021-08-31: Blackstone-affiliated funds completed the QTS acquisition. The transaction price is corporate acquisition consideration, not a Cambois project cost. Original corporate ownership disclosure
Unavailable: no matched, comparable accepted operating-IT target and actual.
Company connections
QTS develops and will operate Cambois; Renaissance Land and Blackstone-affiliated fund ownership are distinct from listed Blackstone’s direct corporate ownership or attributable site earnings.
QTS / Blackstone-affiliated funds research · FJI evidence · Compare · Milestones · European coverage
What remains unverified
Energization, commissioning, accepted customer capacity, current operating IT MW, utilisation, project spending and campus earnings remain unverified. Final detailed permissions, grid/IT basis reconciliation, funded phase budgets, tenant acceptance and actual spend remain open.
Next observable evidence
Verify first-building construction and commissioned service; reconcile 720 MW marketed capacity with reported 1.1 GW power scope.
Sources and claim boundaries
Documents are counted as documents, not independent confirmations. Same-issuer releases and their rewrites share an underlying claim. Six documents across government, QTS, regional investment promotion, independent fDi/Place reporting and Blackstone corporate disclosure. The 2021 acquisition verifies ownership history, not campus financing. Direct local-council news URLs returned 404; national government and independent planning coverage remain available.
- UK Government · 2024-09-25
The UK announces a projected GBP10 billion Blackstone-backed AI data-centre investment at Blyth. This is a planned commitment, not cash spent.
Original project-specific government investment announcement · Announcement and attributed Jon Gray statement · Checked 2026-10-16
- QTS · Document date not displayed; dated subsection retained
QTS identifies its Cambois campus and continuing earthworks in 2026, with first-building construction planned. Its older FAQ schedule is retained as historical wording.
Original company project update · What is happening next? and project FAQ; no first-building completion inferred · Checked 2026-10-16
- Invest Northumberland · Document date not displayed; dated subsection retained
The account identifies QTS as developer/operator and describes ten buildings with a marketed 720 MW total; it does not certify delivered power or precise IT/facility boundary.
Regional investment-promotion project account · Project overview, capacity and phasing paragraphs · Checked 2026-10-16
- fDi Intelligence / Alex Irwin-Hunt · 2026-05-18
fDi reports enabling works from October 2025 and proposed operations in 2029 for the first pair, with four buildings targeted by 2030. Its cited 1.1 GW full-project power figure is not treated as equivalent to the marketed 720 MW.
Independent reporting using planning documents, FOI and company comment · Planning-statement review, Environment Agency permit reporting and company response · Checked 2026-10-16
- Place North East / Sally Gibson · 2026-06-08
Place North East describes applications for remaining enabling works, separately from existing approvals and future building delivery.
Independent local planning reporting · Phases B and C, planning conditions, QTS/Renaissance Land roles · Checked 2026-10-16
- Blackstone · 2021-08-31
Blackstone-affiliated funds completed the QTS acquisition. The transaction price is corporate acquisition consideration, not a Cambois project cost.
Original corporate ownership disclosure · Acquisition close and delisting paragraph · Checked 2026-10-16
AI-assisted public-source research by Fjord Journal. No original interviews, site visits, independent metering or whole-project certification. Planned investment and capacity are excluded from delivered-IT and paid-spending aggregates. Unknown values remain unavailable.
Company investor information & quarterly statements
Blackstone
QTS develops and will operate Cambois; Renaissance Land and Blackstone-affiliated fund ownership are distinct from listed Blackstone’s direct corporate ownership or attributable site earnings.
Official investor & shareholder information · Quarterly financial statements: 2026 Q2
Corporate disclosures provide company-wide context. They do not establish this project’s revenue, spending, profit, ownership share or operating capacity. Disclosure verification records →