Microsoft Kirkkonummi / Kolabacken campus
FJI source-qualified: four-document gate met, including project-specific government evidence. Qualification evidence and decisions →
Published and scoped evidence reviewed October 16, 2026. Historical source events retain their own dates.
Microsoft research · FJI evidence · Compare · Milestones · European coverage
Project at a glance
- Location
- Kolabacken / Masala, Kirkkonummi, Finland
- Status
- Microsoft’s April 2026 update describes first-building interior work and second-building foundations
- Capacity scope
- HEL04 and HEL05–06 phases; accepted IT MW unavailable.
- Business model
- Phased hyperscale cloud and AI-supporting infrastructure
- Next milestone
- Retrieve final HEL05–06 permit and commissioning/utility records for the relevant building.
Representative locality-area pin, not a surveyed campus boundary or entrance.
Project and phase identity
Kolabacken is a distinct physical campus, not another name for Espoo or Vihti. The municipal notice separates HEL04 from HEL05–06.
What changed in the record
The March 2025 municipal notice records the phase-two application. Microsoft’s April 2026 regional release later reports all three campuses’ second-phase permits. This review attributes the later permit assertion to Microsoft; it does not certify the underlying conditions.
Investor read-through
Our analysis: completed earthworks and progressing interiors support a construction classification; neither establishes commissioning or recurring cloud-service output.
Delivery commitments and dated checkpoints
Target: Microsoft’s regional first-phase building-work target is around year-end 2026–2027; service launch to be announced separately.
- 2025-03-14: The municipality distinguishes permitted HEL04 from the then-pending HEL05–06 application LP-257-2024-02386, filed February 14, 2025. Original municipal permit notice
- Undated current source: The April 2026 update reports first-building facade/interior work and second-building foundations at Kirkkonummi; completion of Destia earthworks is not data-centre completion. Original company construction update
- 2026-04-28: Microsoft identifies three separate campuses and phased delivery; first-phase building work targets the turn of 2026–2027, followed by commissioning preparation. Second-phase permits are issuer-reported. Original company disclosure
- 2026-06-09: DCD separately identifies Espoo, Kirkkonummi and Vihti as developments, while attributing site-progress details to Microsoft. Its Vaasa land acquisition is another project. Independent specialist reporting; construction details attributed to Microsoft
- Undated current source: Fortum identifies planned heat recovery from Espoo and Kirkkonummi. The roughly 40% district-heat contribution is a combined future network estimate, not IT capacity or present delivery. Original heat-offtake partner disclosure
Unavailable: no matched, comparable accepted operating-IT target and actual.
Company connections
Microsoft develops the distinct Kolabacken campus. Fortum’s associated heat-recovery infrastructure is separate from Microsoft’s computing operations.
Microsoft research · FJI evidence · Compare · Milestones · European coverage
What remains unverified
Energization, commissioning, accepted customer capacity, current operating IT MW, utilisation, project spending and campus earnings remain unverified. Direct final phase-two permit conditions and current compliance disposition require retrieval.
Next observable evidence
Retrieve final HEL05–06 permit and commissioning/utility records for the relevant building.
Sources and claim boundaries
Documents are counted as documents, not independent confirmations. Same-issuer releases and their rewrites share an underlying claim. Five documents; municipal notice establishes the historical application, not the present final legal disposition. Microsoft site/region updates share an issuer; DCD quotes those updates. Fortum corroborates the heat relationship, not compute commissioning.
- Municipality of Kirkkonummi · 2025-03-14
The municipality distinguishes permitted HEL04 from the then-pending HEL05–06 application LP-257-2024-02386, filed February 14, 2025.
Original municipal permit notice · Paragraphs under the title; phase-one and phase-two scope · Checked 2026-10-16
- Microsoft · Document date not displayed; dated subsection retained
The April 2026 update reports first-building facade/interior work and second-building foundations at Kirkkonummi; completion of Destia earthworks is not data-centre completion.
Original company construction update · Construction update April 2026; Sundsbergin yritystie 19 site-event address · Checked 2026-10-16
- Microsoft · 2026-04-28
Microsoft identifies three separate campuses and phased delivery; first-phase building work targets the turn of 2026–2027, followed by commissioning preparation. Second-phase permits are issuer-reported.
Original company disclosure · Paragraphs 1–5; construction completion and commissioning are separate · Checked 2026-10-16
- DatacenterDynamics / Georgia Butler · 2026-06-09
DCD separately identifies Espoo, Kirkkonummi and Vihti as developments, while attributing site-progress details to Microsoft. Its Vaasa land acquisition is another project.
Independent specialist reporting; construction details attributed to Microsoft · Finland cloud-region background and links to all three local project updates · Checked 2026-10-16
- Fortum · Document date not displayed; dated subsection retained
Fortum identifies planned heat recovery from Espoo and Kirkkonummi. The roughly 40% district-heat contribution is a combined future network estimate, not IT capacity or present delivery.
Original heat-offtake partner disclosure · Data centers provide electricity-based district heating; combined two-site scope · Checked 2026-10-16
AI-assisted public-source research by Fjord Journal. No original interviews, site visits, independent metering or whole-project certification. Planned investment and capacity are excluded from delivered-IT and paid-spending aggregates. Unknown values remain unavailable.
Company investor information & quarterly statements
Microsoft
Microsoft develops the distinct Kolabacken campus. Fortum’s associated heat-recovery infrastructure is separate from Microsoft’s computing operations.
Official investor & shareholder information · Quarterly financial statements: FY2026 Q4, quarter ended June 30, 2026
Fortum
Heat-recovery partner; separate from Microsoft computing operations.
Official investor & shareholder information · Quarterly financial statements: January–June 2026; includes April–June quarter
Corporate disclosures provide company-wide context. They do not establish this project’s revenue, spending, profit, ownership share or operating capacity. Disclosure verification records →