Norway · Nordfjord · FJ Intelligence Project Research

Lefdal Mine Data Centers / Olivia

Operating underground AI/HPC campus at Nordfjord; Olivia inaugurated in 2025 and expanded in 2026. Full-campus operating IT load remains undisclosed.

Project stage Operating

FJ Intelligence Evidence

What the record establishes

Evidence base
10 reviewed documents
Current stage
Operational; expansion ongoing
Available electrical power
80 MW · operator-reported
Olivia accelerators
448 · Sigma2-reported

Investment takeaway

Mine reuse and fjord cooling can reduce surface construction and cooling demand. The investment test is conversion of available infrastructure into contracted, occupied and paid service. The 3i acquisition provides ownership exposure; its purchase price includes renewable assets and cannot be treated as new campus construction spending.

Project at a glance

Location
Nordfjordvegen 7300, 6770 Nordfjordeid, Vestland, Norway
Project scope
AI and high-performance-computing colocation campus
Named participants
Lefdal Mine Data Centers; 3i Infrastructure / co-investors; Sigma2; HPE; AMD; NVIDIA
Capacity boundary
80 MW available electrical power reported by operator; 200 MW last-mile grid infrastructure. Neither is measured operating IT load. Olivia: 448 Grace Hopper chips per Sigma2.
Map precision
Operator-published visitor reference; approximate campus location, not underground hall coordinates.

FJI source-qualified: four-document gate met, including project-specific government evidence. Qualification evidence and decisions →

A mine reused for computing

The campus occupies a former olivine mine beside Nordfjord. Underground halls reuse an existing industrial excavation; generators, offices and other equipment remain above ground. It is an example of adapting industrial infrastructure to its setting, rather than proof of an untouched landscape. [S4, S9]

What has actually been delivered

Olivia opened on June 17, 2025. Sigma2 subsequently reported expansion from 304 to 448 Grace Hopper chips. NIRD storage has been operational since 2022. These are identified customer systems with dated delivery evidence, rather than a claim that the mine’s full potential has been fitted out. [S1, S2, S8]

Electrical capacity is not server consumption

Lefdal reports 80 MW available power and 200 MW reinforced last-mile grid infrastructure. Its facility page assigns 80 MW to Level 3. No metered whole-campus IT draw was located; empty chambers, electrical infrastructure and occupied computing capacity are not equivalent. [S3, S4]

Cooling follows the local geography

Seawater supplies heat exchangers, which cool a separate freshwater loop serving equipment. The operator describes modular cooling and indicative PUE 1.08–1.15; this profile does not certify those figures at current utilization. Heat reuse is described by Sigma2, but annual delivered heat, environmental discharge monitoring and realized income remain open. [S5, S8]

Ownership changed in 2026

The acquisition disclosure is more precise than the operator’s shorthand 90% ownership statement: 3i-managed interests total 90%, while listed 3i Infrastructure directly holds just over 45%. About €263 million includes renewable assets. Its latest half-year reporting is linked below; neither investment valuation nor portfolio income is mine-only operating profit. [S6, S7]

Technology and commercial participants

Sigma2 is the research customer and system owner; HPE delivered the Cray system, using AMD CPUs and NVIDIA Grace Hopper accelerators. Their roles establish technology exposure, not current supplier backlog, recurring site revenue or a campus-wide hardware count. [S1, S2]

What remains unverified

Current occupied IT MW, tenant utilization, phase-specific permits and utility terms, mine-only revenue, paid campus capex, discharge monitoring and delivered heat volumes are not established. Full corporate certification remains held pending current supplier financial and ownership reconciliation.

Next evidence checkpoint

Seek dated phase-level commissioning and measured operating IT load, customer acceptance, site financial allocation and independently supported environmental performance.

Delivery timing

Olivia inaugurated June 17, 2025; 2026 GPU expansion reported. Additional mine halls remain a phased development opportunity, with no verified full-campus completion date.

Related Nordic Projects

EcoDataCenter Falun · Mistral / EcoDataCenter Borlänge

Investor and financial disclosures

These links provide corporate context. They do not establish project-specific supplier revenue or site returns. Complete supplier quarterly and ownership reconciliation remains outstanding.

Sources and claim boundaries

  1. Norwegian government — Olivia inauguration

    Government confirms Olivia opened at Lefdal on June 17, 2025, delivered by HPE, with NOK 225 million invested in the system. This is a supercomputer investment, not campus construction spending.

    Document date: 2025-06-17 · Reviewed November 17, 2026. Government confirms Olivia opened at Lefdal on June 17, 2025, delivered by HPE, with NOK 225 million invested in the system. This is a supercomputer investment, not campus construction spending.

  2. Sigma2 — GPU expansion

    Sigma2 reports 144 additional GPUs, bringing Olivia to 448 NVIDIA Grace Hopper chips from its original 304. The page is dated February 27, 2026; the news index lists March 2. This measures the named system, not all equipment in the mine.

    Document date: 2026-02-27 · Reviewed November 17, 2026. Sigma2 reports 144 additional GPUs, bringing Olivia to 448 NVIDIA Grace Hopper chips from its original 304. The page is dated February 27, 2026; the news index lists March 2. This measures the named system, not all equipment in the mine.

  3. Lefdal — power expansion

    Operator reports available power increased from 20 MW to 80 MW through a 132 kV connection; last-mile grid reinforced to 200 MW. These are electrical infrastructure figures, not measured IT consumption.

    Document date: undated · Reviewed November 17, 2026. Operator reports available power increased from 20 MW to 80 MW through a 132 kV connection; last-mile grid reinforced to 200 MW. These are electrical infrastructure figures, not measured IT consumption.

  4. Lefdal — facility

    Former olivine mine has six levels, 75 chambers and up to 120,000 m² potential white space. Level 3 is described as 80 MW. Future space and capacity are not fully fitted or occupied halls.

    Document date: undated · Reviewed November 17, 2026. Former olivine mine has six levels, 75 chambers and up to 120,000 m² potential white space. Level 3 is described as 80 MW. Future space and capacity are not fully fitted or occupied halls.

  5. Lefdal — cooling

    Operator describes seawater drawn from 100 m depth, heat exchangers isolating a closed freshwater circuit, and indicative PUE 1.08–1.15. Cooling capacity and electrical/IT power are different quantities; efficiency is not independently metered here.

    Document date: undated · Reviewed November 17, 2026. Operator describes seawater drawn from 100 m depth, heat exchangers isolating a closed freshwater circuit, and indicative PUE 1.08–1.15. Cooling capacity and electrical/IT power are different quantities; efficiency is not independently metered here.

  6. 3i Infrastructure — completed acquisition

    September 3 disclosure confirms about €263m invested, including renewable assets. 3i manages 90%: listed 3i Infrastructure holds just over 45%, co-investors approximately 45%; minority retains 10%. Acquisition price is not campus capex.

    Document date: 2026-09-03 · Reviewed November 17, 2026. September 3 disclosure confirms about €263m invested, including renewable assets. 3i manages 90%: listed 3i Infrastructure holds just over 45%, co-investors approximately 45%; minority retains 10%. Acquisition price is not campus capex.

  7. 3i Infrastructure — September 2026 half-year report

    November 9 financial report records LMD investment and valuation; LMD includes a small renewable portfolio. Actual financial statements were reviewed, but they do not establish mine-only earnings or paid construction expenditure.

    Document date: 2026-11-09 · Reviewed November 17, 2026. November 9 financial report records LMD investment and valuation; LMD includes a small renewable portfolio. Actual financial statements were reviewed, but they do not establish mine-only earnings or paid construction expenditure.

  8. Sigma2 — data-centre strategy

    NIRD storage has operated at Lefdal since 2022. Sigma2 describes a heat-reuse agreement with Sjømatstaden; delivered annual heat and commercial proceeds are not quantified. Some launch wording is stale and superseded by the inauguration and 2026 expansion.

    Document date: undated · Reviewed November 17, 2026. NIRD storage has operated at Lefdal since 2022. Sigma2 describes a heat-reuse agreement with Sjømatstaden; delivered annual heat and commercial proceeds are not quantified. Some launch wording is stale and superseded by the inauguration and 2026 expansion.

  9. Lefdal — visitor location

    Operator gives Nordfjordvegen 7300, 6770 Nordfjordeid and coordinates 61.937854602233884, 5.539545223336609. Map uses this operator visitor reference, not a surveyed underground hall position.

    Document date: undated · Reviewed November 17, 2026. Operator gives Nordfjordvegen 7300, 6770 Nordfjordeid and coordinates 61.937854602233884, 5.539545223336609. Map uses this operator visitor reference, not a surveyed underground hall position.

  10. Data Center Dynamics — Lefdal site report

    Independent site reporting describes the underground campus and Olivia installation, corroborating the reuse of mine infrastructure. Does not independently certify current full-campus IT load or project returns.

    Document date: undated · Reviewed November 17, 2026. Independent site reporting describes the underground campus and Olivia installation, corroborating the reuse of mine infrastructure. Does not independently certify current full-campus IT load or project returns.

Map reference: Published facility location. Operator-published visitor reference; approximate campus location, not underground hall coordinates.

AI-assisted public-source research by Fjord Journal. No site visit, private contract inspection or independent metering. Unknown operating IT load and paid capital remain undisclosed; no whole-project certification or investment recommendation is claimed.

Company investor information & quarterly statements

Financial-disclosure review remains incomplete for one or more participants. The company-level limitations below remain unresolved; this section does not establish full corporate-disclosure verification.

Corporate disclosures provide company-wide context. They do not establish this project’s revenue, spending, profit, ownership share or operating capacity. Disclosure verification records →