Project directory / EcoDataCenter 1 / Falun AI Campus
EcoDataCenter 1 / Falun AI Campus
Operating timber-built AI/HPC campus in Falun; DeepL Blackwell deployment documented, while latest quarterly reporting describes campus completion still approaching.
Project stage Operating
What the record establishes
- Evidence base
- 11 reviewed documents
- Current stage
- Operational; expansion ongoing
- Power marketed
- 80 MW · available power
- Historical capacity
- 41 MW · end 2025
Primary documents
- Falun municipality — Ingarvet land agreement
- EcoDataCenter — Falun site
- EcoDC Holding —2025 annual financial statements
- EcoDC Holding —Q3 2026 interim report
- EcoDataCenter —DeepL Blackwell deployment
- DeepL —Arion deployment
- Stora Enso —Falun timber construction
- EcoDataCenter —2024 sustainability report
- PeeringDB —Falun facility record
- EcoDataCenter —CoreWeave partnership
Investment takeaway
Falun combines a delivered AI installation with phased capacity growth, mass timber and energy-system integration. These are useful design and commercial differentiators; investment value still depends on accepted customer service, utilization and cash generation. Group financing and attractive architecture do not establish Falun-specific returns.
Project at a glance
- Location
- Slaggvarpsvägen 21, 791 77 Falun, Dalarna, Sweden
- Project scope
- AI and high-performance-computing colocation campus
- Named participants
- EcoDataCenter / Areim; DeepL; CoreWeave; NVIDIA; Stora Enso; ByggPartner; Schneider Electric
- Capacity boundary
- 80 MW available power marketed; 41 MW capacity at end 2025 in annual report; 65 MW targeted after E/F completion. These are distinct dates/bases, not current measured IT load.
- Map precision
- PeeringDB facility geocode matched to operator street address; approximate campus reference, not surveyed.
FJI source-qualified: four-document gate met, including project-specific government evidence. Qualification evidence and decisions →
A separate campus from Borlänge
This record covers EcoDataCenter 1 at Ingarvet in Falun. It is distinct from EcoDataCenter 2 at Kvarnsveden, Borlänge and from Mistral’s planned deployment there. Shared ownership and regional heat studies are not a basis for merging site capacity or customers. [S2, S3]
Timber and planted roofs
Stora Enso documents cross-laminated-timber construction with ByggPartner, structural engineer Limträteknik and Nordisk Kombination Arkitekter. The operator documents sedum roofs. These choices connect the architecture to regional building materials, but do not prove zero environmental impact or a lifecycle carbon balance for every building. [S7, S8]
AI use is demonstrated
EcoDataCenter identifies DeepL’s liquid-cooled GB200 deployment at Falun; DeepL independently confirms the Arion system was deployed in 2025. CoreWeave is another named campus partner. Neither source provides a total current site GPU count or customer-level accepted MW. [S5, S6, S11]
Capacity changes require dated evidence
The 2025 annual report records 41 MW campus capacity and a 65 MW target after E/F, with F originally targetedQ3 and E lateQ4 2026. The November 11 Q3 report says Falun is nearing completion; it does not establish final E/F acceptance. The current 80 MW available-power headline is retained separately. [S2, S3, S4]
Land, power and community integration
Falun municipality confirms a land agreement enabling expansion at Ingarvet through relocation of a driving practice facility. It is not a complete building-permit or grid acceptance record. The operator describes renewable power and heat reuse with the local energy system; current metered heat, water and site-specific electricity performance still require evidence. [S1, S2]
Ownership and financing
EcoDC Falun AB operates the site under EcoDC Holding. Its annual report records Areim Investment DC AB’s 97.6% parent holding at end 2025; that date is retained. The Q3 report includes a new 1.5 MW Falun customer agreement and group financial statements. Signed demand is distinct from delivered service, and consolidated cash flow is not allocated to Falun here. [S3, S4]
What remains unverified
Current commissioned E/F capacity, site-metered IT draw, customer acceptance and utilization, final permits and utility terms, full-campus GPU count, measured heat/water performance and Falun-only financial results remain unverified. Complete current public-supplier financial and corporate ownership reconciliation remains held.
Next evidence checkpoint
Seek dated phase-level commissioning and measured operating IT load, customer acceptance, site financial allocation and independently supported environmental performance.
Delivery timing
First facility opened 2019. E/F had historicalQ3/Q4 2026 targets. November 11 Q3 reporting says nearing campus completion; final commissioning dates remain unverified.
Related Nordic Projects
Lefdal Mine / Olivia · Mistral / EcoDataCenter Borlänge
Investor and financial disclosures
These links provide corporate context. They do not establish project-specific supplier revenue or site returns. Complete supplier quarterly and ownership reconciliation remains outstanding.
- EcoDataCenter investor information · Q3 2026 financial statements · 2025 annual financial statements and ownership (reviewed November 17, 2026).
- CoreWeave — official investor information; current quarterly-statement review remains pending for this project.
- NVIDIA — official investor information; current quarterly-statement review remains pending for this project.
- Stora Enso — official investor information; current quarterly-statement review remains pending for this project.
- Schneider Electric — official investor information; current quarterly-statement review remains pending for this project.
- ByggPartner — official investor information; current quarterly-statement review remains pending for this project.
Sources and claim boundaries
- Falun municipality — Ingarvet land agreement
Municipality confirms an agreement enabling EcoDataCenter expansion at Ingarvet by relocating the driving practice site. This establishes local land arrangements, not every permit, completed expansion or electricity delivery.
Document date: 2024-01-26 · Reviewed November 17, 2026. Municipality confirms an agreement enabling EcoDataCenter expansion at Ingarvet by relocating the driving practice site. This establishes local land arrangements, not every permit, completed expansion or electricity delivery.
- EcoDataCenter — Falun site
Operator lists 80 MW total available power at Slaggvarpsvägen 21, with renewable electricity and PUE1.2. Available power is not commissioned or operating IT capacity. Heat-reuse and power-mix descriptions are operator claims.
Document date: undated · Reviewed November 17, 2026. Operator lists 80 MW total available power at Slaggvarpsvägen 21, with renewable electricity and PUE1.2. Available power is not commissioned or operating IT capacity. Heat-reuse and power-mix descriptions are operator claims.
- EcoDC Holding —2025 annual financial statements
Annual report states Falun capacity reached 41 MW at end 2025 and projects 65 MW after E/F delivery; F targetedQ3 and E lateQ4 2026. It identifies EcoDC Falun AB as operator and Areim Investment DC AB as 97.6% owner of EcoDC Holding at that balance-sheet date. Historical targets are not current commissioning proof.
Document date: undated · Reviewed November 17, 2026. Annual report states Falun capacity reached 41 MW at end 2025 and projects 65 MW after E/F delivery; F targetedQ3 and E lateQ4 2026. It identifies EcoDC Falun AB as operator and Areim Investment DC AB as 97.6% owner of EcoDC Holding at that balance-sheet date. Historical targets are not current commissioning proof.
- EcoDC Holding —Q3 2026 interim report
November 11 interim reports Falun nearing campus completion and a new 1.5 MW customer contract signed inQ3. Contracted demand is not operating IT load. Income, balance-sheet and cash-flow statements reviewed; group results are not Falun-specific. Report is unaudited.
Document date: 2026-11-11 · Reviewed November 17, 2026. November 11 interim reports Falun nearing campus completion and a new 1.5 MW customer contract signed inQ3. Contracted demand is not operating IT load. Income, balance-sheet and cash-flow statements reviewed; group results are not Falun-specific. Report is unaudited.
- EcoDataCenter —DeepL Blackwell deployment
Operator reports DeepL liquid-cooled DGX GB200 deployment at Falun. Named collaboration includes NVIDIA and Schneider. This supports a real AI installation, not total campus GPU count or supplier revenue.
Document date: undated · Reviewed November 17, 2026. Operator reports DeepL liquid-cooled DGX GB200 deployment at Falun. Named collaboration includes NVIDIA and Schneider. This supports a real AI installation, not total campus GPU count or supplier revenue.
- DeepL —Arion deployment
DeepL confirms its Arion DGX SuperPOD with GB200 systems was deployed in 2025 for AI model training and deployment. No total campus GPU fleet or site-specific financial results disclosed.
Document date: 2025-09-03 · Reviewed November 17, 2026. DeepL confirms its Arion DGX SuperPOD with GB200 systems was deployed in 2025 for AI model training and deployment. No total campus GPU fleet or site-specific financial results disclosed.
- Stora Enso —Falun timber construction
Supplier documents mass timber construction, 2019 opening and roles of ByggPartner, Limträteknik and Nordisk Kombination Arkitekter. Supplier narrative is not an independent whole-life environmental audit.
Document date: 2025-11-04 · Reviewed November 17, 2026. Supplier documents mass timber construction, 2019 opening and roles of ByggPartner, Limträteknik and Nordisk Kombination Arkitekter. Supplier narrative is not an independent whole-life environmental audit.
- EcoDataCenter —2024 sustainability report
Operator documents sedum roofs at Falun. Planted roofs are a design feature; they do not demonstrate zero habitat impact, net-zero operation or complete biodiversity compensation.
Document date: undated · Reviewed November 17, 2026. Operator documents sedum roofs at Falun. Planted roofs are a design feature; they do not demonstrate zero habitat impact, net-zero operation or complete biodiversity compensation.
- The Guardian —Falun visit
Independent reporter visited Falun and described timber construction. Environmental claims remain attributed.
Document date: 2026-11-12 · Reviewed November 17, 2026. Independent reporter visited Falun and described timber construction. Environmental claims remain attributed.
- PeeringDB —Falun facility record
Facility record matches Slaggvarpsvägen 21 and provides 60.610531, 15.610386. Used as an approximate campus map reference; not a survey.
Document date: undated · Reviewed November 17, 2026. Facility record matches Slaggvarpsvägen 21 and provides 60.610531, 15.610386. Used as an approximate campus map reference; not a survey.
- EcoDataCenter —CoreWeave partnership
Operator identifies CoreWeave collaboration at Falun; no customer-specific accepted load, contract value or recurring revenue is established by the page.
Document date: undated · Reviewed November 17, 2026. Operator identifies CoreWeave collaboration at Falun; no customer-specific accepted load, contract value or recurring revenue is established by the page.
Map reference: Published facility location. PeeringDB facility geocode matched to operator street address; approximate campus reference, not surveyed.
AI-assisted public-source research by Fjord Journal. No site visit, private contract inspection or independent metering. Unknown operating IT load and paid capital remain undisclosed; no whole-project certification or investment recommendation is claimed.
Company investor information & quarterly statements
Financial-disclosure review remains incomplete for one or more participants. The company-level limitations below remain unresolved; this section does not establish full corporate-disclosure verification.
Corporate disclosures provide company-wide context. They do not establish this project’s revenue, spending, profit, ownership share or operating capacity. Disclosure verification records →