Equinix SG6, Singapore
FJI source-qualified: four-document gate met, including project-specific government evidence. Qualification evidence and decisions →
Equinix opened SG6’s first phase on November 6, 2026. Its 20 MW IT figure describes full build-out, with actual utilization undisclosed.
What the record establishes
- Evidence base
- 5 reviewed documents
- Current stage
- First phase opened November 6, 2026; expansion distinct
- First-phase scope
- 8 MW stated; about 1,550 cabinets
- Ultimate scope
- 20 MW IT at full build-out
Investment takeaway
Opening a first phase adds a tangible delivery milestone, but the investment case depends on customer occupancy, billing and the capital required for later expansion. The full-build IT figure, available cabinets and announced investment measure different things; none establishes the facility’s return or cash contribution.
Project at a glance
- Location
- 21 Jalan Tukang, Singapore 619794
- Project scope
- AI-ready IBX colocation; operating first phase and later expansion
- Named participants
- Equinix Inc. (NASDAQ: EQIX)
- Capacity boundary
- 8 MW stated first phase; 20 MW IT full-build scope. Delivered cabinets do not measure occupancy.
- Map precision
- SLA OneMap matched address point; approximate site vicinity, not gate, equipment, parcel boundary or data hall.
Opening and expansion are separate
The operating milestone covers an initial phase. Full-build capacity remains a later expansion scope, without a disclosed final date or measured utilization series. The ministry’s launch speech confirms opening but does not certify every planned system. [1, 2]
The plan changed between announcement and opening
Equinix’s November 2024 announcement expected first-quarter 2027 opening and an initial investment above US$260 million. Its November 2026 release reports the earlier opening and approximately US$290 million initial investment. Those are different dated plans and milestones. They do not establish paid expenditure or a final life-cycle budget. [2, 4]
AI capability and environmental targets
Liquid-cooling capability, a design PUE of 1.20 and targeted Green Mark Platinum certification are operator statements, not measured performance or an awarded certificate. No specific GPU installation or customer order is established. Portfolio renewable-energy coverage is distinct from round-the-clock carbon-free physical supply. [2, 4]
A further research milestone is planned
The ministry describes a National University of Singapore co-innovation facility planned for 2027. It was not open at launch. Research partnerships may support later improvements, but no quantified operating gain or earnings contribution is assigned. [1]
Location and financial context
CBRE’s own October property commentary identifies SG6 at 21 Jalan Tukang. OneMap matches the address. The pin is a qualified address reference, not an operator-confirmed entrance. Equinix’s latest quarterly reports provide group context; project-level rent, profit and return remain undisclosed. [5]
What remains unverified
Full-build expansion schedule; occupied cabinets and contracted demand; facility-level revenue and capital spent; measured PUE and water use; awarded environmental certification; utility service terms and exact entrance.
Next evidence checkpoint
Track occupied cabinets, billed service, further phase commissioning, measured efficiency and delivery of the planned co-innovation facility.
Delivery timing
First phase opened November 6, 2026; the co-innovation facility is planned for 2027. No full-build service date verified.
Related Singapore projects
- Nxera DC Tuas, Singapore · Singapore
Sources and claim boundaries
- MDDI ministerial launch address · November 6, 2026
Acknowledges SG6’s opening and its connection to the capacity-allocation framework; it is not acceptance of all planned capacity.
Document date: 2026-11-06 · Reviewed November 15, 2026. Supports the described project and phase only; not independent metering or project earnings.
- Equinix opening release · November 6, 2026
Describes an 8 MW first phase, about 1,550 cabinets and 20 MW IT at full build-out, with approximately US$290 million initial investment.
Document date: 2026-11-06 · Reviewed November 15, 2026. Supports the described project and phase only; not independent metering or project earnings.
- Data Center Dynamics · November 10, 2026
Reports the launch and distinguishes the Jalan Tukang building, earlier schedule and full-build capacity; figures remain attributed.
Document date: 2026-11-10 · Reviewed November 15, 2026. Supports the described project and phase only; not independent metering or project earnings.
- Equinix original project announcement · November 19, 2024
The original US$260 million plan and first-quarter 2027 opening expectation are historical; the November 2026 release supplies the updated milestone.
Document date: 2024-11-19 · Reviewed November 15, 2026. Supports the described project and phase only; not independent metering or project earnings.
- CBRE original research commentary · October 22, 2026
Identifies SG6 at 21 Jalan Tukang. Reported property completion is distinct from the operator’s November service-opening milestone.
Document date: 2026-10-22 · Reviewed November 15, 2026. Supports the described project and phase only; not independent metering or project earnings.
Map reference: Singapore Land Authority OneMap. SLA OneMap matched address point; approximate site vicinity, not gate, equipment, parcel boundary or data hall.
AI-assisted public-source research by Fjord Journal. No site visit, private contract inspection or independent metering. Unknown operating IT load and paid capital remain undisclosed; no whole-project certification or investment recommendation is claimed.
Company financial disclosures
These are company-wide reports for the roles identified in this profile. They do not allocate project revenue, bank lending shares, contract margins or investment returns.
Company investor information & quarterly statements
Financial-disclosure review remains incomplete for one or more participants. The company-level limitations below remain unresolved; this section does not establish full corporate-disclosure verification.
Corporate disclosures provide company-wide context. They do not establish this project’s revenue, spending, profit, ownership share or operating capacity. Disclosure verification records →
