Concord Locke Road Micro Data Center
FJI source-qualified: four-document gate met, including project-specific government evidence. Qualification evidence and decisions →
A proposed data center at 52 Locke Road remains in local review. The applicant requested a December 16 continuation; final approval and construction are unverified.
What the record establishes
- Evidence base
- 5 reviewed documents
- Current stage
- Proposed; local site-plan review pending
- Power boundary
- 15 MW proposed transformer
- Building proposal
- 8,160 square feet; approval pending
Investment takeaway
The micro label describes a compact building, not a small electrical requirement. The decisive milestones are local permission and an executable utility-service plan. Immersion cooling could reduce routine cooling-water needs, but proposed design and promotional revenue estimates do not establish operating performance or returns.
Project at a glance
- Location
- 52 Locke Road, Concord, New Hampshire, United States
- Project scope
- Proposed pilot colocation/AI computing facility
- Named participants
- Granite Municipal Manufacturing & Sales LLC; Levitate; Northpoint Engineering
- Capacity boundary
- 15 MW proposed transformer rating; 13.5 MW server-load estimate attributed to the CEO in independent reporting. Neither establishes energized service.
- Map precision
- Approximate Census street-address reference for the documented address; not a surveyed building or parcel boundary.
The proposal and its participants
City records identify Northpoint Engineering as the presenter for Granite Municipal Manufacturing & Sales LLC. The proposal includes 7,220 square feet of data-center space within the building. Reporting identifies Levitate’s technology role. No construction start is verified. [1, 2, 5]
The planning process is not finished
Draft minutes record a 9–0 continuation vote on October 21. The city later said the applicant requested December 16 and that November 18 would address continuation only. September’s Passed docket label concerns the application stage, not final site-plan approval. [1, 2, 3]
Separate transformer capacity from computing load
The 15 MW transformer is proposed. October reporting attributes a separate 13.5 MW server-load estimate to the CEO, excluding overhead. Neither figure establishes contracted service or current consumption. The board sought additional grid-impact evidence. [1, 4]
Cooling and demand remain design claims
Applicant statements describe closed-loop immersion cooling; no operating measurements were found in the reviewed sources. Reporting describes customers owning servers and leasing space. No named customer, executed lease or independently supported revenue forecast has been verified. [1, 5]
What remains unverified
Final site-plan decision; executed utility-service agreement and independent grid analysis; construction schedule; installed hardware; tenants; capital cost and financing; demonstrated cooling and workload performance.
Next evidence checkpoint
Check the November 18 continuation vote, the requested December 16 hearing and the applicant’s responses on grid effects, expansion and utility service.
Delivery timing
Applicant requested continuation to December 16, 2026. City says November 18 would address the continuation vote, without merits discussion; the request is not an approval.
Related Northeast projects
- New Jersey Supercomputer Initiative · New Jersey
- Aligned IAD-06, Frederick · Maryland
- MGHPCC AI Compute Resource, Holyoke · Massachusetts
- Servistar Westfield Data Center Campus · Massachusetts
Sources and claim boundaries
- City of Concord · October 21, 2026 draft Planning Board minutes
Pages 25–37 describe the application, proposed transformer, applicant statements and continued hearing; they do not record final site-plan approval.
Reviewed November 15, 2026.
- City of Concord · September 16, 2026 application docket
Identifies the applicant, address, parcel and proposed building. The initial application disposition is separate from final approval.
Reviewed November 15, 2026.
- City of Concord · November planning-meeting update
Says the applicant requested a December 16 continuation and describes a November 18 continuation vote, without merits discussion.
Reviewed November 15, 2026.
- Concord Monitor / NHPR · October 26, 2026
Reports deferred review and attributes the 13.5 MW server-load estimate to the CEO; grid and utility questions remain open.
Reviewed November 15, 2026.
- NHPR · October 20, 2026
Reports the pilot proposal, applicant interviews and intended customer model. Proposed cooling, schedules and commercial claims remain unproven.
Reviewed November 15, 2026.
Map reference: U.S. Census address geocoder. Approximate Census street-address reference for the documented address; not a surveyed building or parcel boundary.
AI-assisted public-source research by Fjord Journal. No site visit, private contract inspection or independent metering. Unknown operating IT load and paid capital remain undisclosed; no whole-project certification or investment recommendation is claimed.
Company investor information & quarterly statements
Financial-disclosure review remains incomplete for one or more participants. The company-level limitations below remain unresolved; this section does not establish full corporate-disclosure verification.
Corporate disclosures provide company-wide context. They do not establish this project’s revenue, spending, profit, ownership share or operating capacity. Disclosure verification records →