Aligned IAD-06, Frederick
FJI source-qualified: four-document gate met, including project-specific government evidence. Qualification evidence and decisions →
Turner reported structural topping-out on March 9, 2026. No later IAD-06 construction milestone, commissioning or customer acceptance was verified in this review.
What the record establishes
- Evidence base
- 7 reviewed documents
- Current stage
- Construction milestone reported March 9, 2026; operation unverified
- Capacity boundary
- 72 MW stated; electrical basis unspecified
- Building scale
- 450,000 square feet; two stories
Investment takeaway
The completed structural frame is tangible delivery progress, but saleable computing capacity depends on electrical service, equipment commissioning and customer acceptance. The investment question is the conversion of a construction milestone into contracted, available service. No IAD-06 capital budget, revenue or return has been verified.
Project at a glance
- Location
- 5601 Manor Woods Road, Frederick, Maryland, United States
- Project scope
- Commercial data center; AI-ready cooling design, workloads undisclosed
- Named participants
- Aligned Data Centers; Turner Construction
- Capacity boundary
- 72 MW contractor-described facility capacity; IT-load versus utility-power basis unspecified. 450,000 square feet across two stories.
- Map precision
- Approximate Census street-address reference for the campus, not the IAD-06 building.
A building within a much larger redevelopment
IAD-06 is part of Aligned’s 75-acre Frederick campus. Turner describes a two-story building with hybrid liquid and air cooling. This Aligned parcel is separate from the larger former Eastalco industrial redevelopment; master-park capacity is not assigned to the building. [1, 4, 5]
What topping-out establishes
The contractor’s March release establishes structural progress, without defining the electrical basis of its 72 MW rating. The retained construction classification is dated; it does not establish current site activity or opening. [1]
Permits have a campus boundary
Maryland’s January 30, 2025 permit names Aligned Data Centers (MD) PropCo LLC and the campus address at 5601 Manor Woods Road. It authorizes emergency-generation equipment at campus scale. The May county agenda lists three additional buildings on the Aligned parcel; an agenda is an application record, not final approval. Neither document proves IAD-06 operating acceptance or turns backup generator ratings into IT load. [2, 3]
Ownership changed; project economics remain private
Aligned announced that the AIP, MGX and BlackRock GIP consortium completed its acquisition on July 21, 2026. This is ownership of the platform. Companywide transaction values and growth-capital commitments are not the construction cost of IAD-06. Turner is the named contractor; public parent-group financial reports provide corporate context without a project-level allocation. [7]
Owner and contractor financial context
Aligned is a private operating platform. BlackRock’s GIP ownership relationship and Turner’s contractor role do not establish the value or profitability of this building.
- BlackRock: Investor relations · Latest reviewed financial update
- HOCHTIEF: Investor relations · Latest reviewed financial update
What remains unverified
Latest on-site construction progress; capacity measurement basis; commissioning and occupancy evidence; confirmed electrical service; customer identity or acceptance; project capital budget, financing and paid spending.
Next evidence checkpoint
Obtain a dated IAD-06 commissioning or occupancy record, electrical-service evidence, capacity definition and customer acceptance.
Delivery timing
No verified IAD-06 commercial opening date. March 9 is a completed structural milestone, not an operating target.
Related Northeast projects
- New Jersey Supercomputer Initiative · New Jersey
- Concord Locke Road Micro Data Center · New Hampshire
- MGHPCC AI Compute Resource, Holyoke · Massachusetts
- Servistar Westfield Data Center Campus · Massachusetts
Sources and claim boundaries
- Turner Construction · March 9, 2026
Documents structural topping-out, building size and cooling design. Its 72 MW description does not define the electrical measurement basis.
Reviewed November 15, 2026.
- Maryland Department of the Environment · Issued campus permit, January 30, 2025
Identifies the campus permit holder and address and authorizes emergency generators; it is not IAD-06 operating acceptance.
Reviewed November 15, 2026.
- Frederick County Planning Commission · May 14, 2025 agenda
Identifies an application for three additional campus buildings. A scheduled planning item does not itself establish final approval.
Reviewed November 15, 2026.
- Aligned Data Centers · Maryland campus overview
Describes the 75-acre campus; its listed address is attached to IAD-04, not a separately verified IAD-06 entrance.
Reviewed November 15, 2026.
- Data Center Dynamics · May 23, 2025
Provides independent planning context for the additional buildings and distinguishes Aligned’s parcel from the larger industrial redevelopment.
Reviewed November 15, 2026.
- Data Center Dynamics · March 12, 2026
Reports Turner’s topping-out announcement. It is not counted as a separate underlying construction-milestone source.
Reviewed November 15, 2026.
- Aligned ownership announcement · July 21, 2026
Confirms the consortium’s completed platform acquisition. Companywide transaction and growth-capital figures are not assigned to IAD-06.
Reviewed November 15, 2026.
Map reference: U.S. Census address geocoder. Approximate Census street-address reference for the campus, not the IAD-06 building.
AI-assisted public-source research by Fjord Journal. No site visit, private contract inspection or independent metering. Unknown operating IT load and paid capital remain undisclosed; no whole-project certification or investment recommendation is claimed.
Company investor information & quarterly statements
Financial-disclosure review remains incomplete for one or more participants. The company-level limitations below remain unresolved; this section does not establish full corporate-disclosure verification.
Corporate disclosures provide company-wide context. They do not establish this project’s revenue, spending, profit, ownership share or operating capacity. Disclosure verification records →