AI computing · Expansion and power delivery

Colossus 2 / Memphis–Southaven Expansion

FJI source-qualified: four-document gate met, including project-specific government evidence. Qualification evidence and decisions →

Expansion under construction; customer access disclosed, but current building-level commissioned IT load and power acceptance remain unverified.

Published and sources reviewed November 14, 2026.

Compare this project · Track milestones

Investment takeaway

Rapid construction can shorten the route to revenue, but only sustained power and accepted customer capacity make that capital productive. Generation nameplate, facility demand, IT load and stored energy require separate accounting.

Which Site Does This Cover?

This record covers the later Colossus 2 expansion footprint across the Memphis–Southaven border. It is separate from Colossus 1 in Memphis. SemiAnalysis uses Macrohard, MiniHard, Macroharder, Project SPAM and Gun Range to describe buildings or phases; those aliases are not treated here as independently commissioned campuses. The Mississippi Stanton Road generation facility is supporting infrastructure, not an additional data-center campus in this inventory.

Evidence and Sources

MDEQ identifies the SPAM facility at 2929 Stateline Road West, Southaven. Construction general-permit coverage MSR120004 was issued October 16, 2026; the database lists January 31, 2027 as its end date. This establishes a stormwater record, not data-hall commissioning. MDEQ →

The July 30 agreed order concerns 69 temporary gas turbines at the separate Stanton Road power facility. It records supply-chain delays to permanent units and sets unit-specific retirement dates, including December 31, 2026 for specified units and July 14, 2027 for the latest units. It does not measure current net power delivered to computing. Mississippi Commission on Environmental Quality →

March Permit Board minutes describe MZX’s application for 41 permanent gas turbines at 2875 Stanton Road, about 1.2 GW behind the meter. This is a generation project, separate from IT capacity; permitting does not establish commissioned output. MDEQ Permit Board →

On May 28 Anthropic said its SpaceX agreements covered access to GPU capacity in both Colossus 1 and Colossus 2. It did not disclose the building allocation, current site utilization or Colossus 2 revenue in that statement. Anthropic →

SemiAnalysis’s November 3 analysis describes rapid expansion across the Memphis–Mississippi border and estimates nearly 6 GWh of battery storage. Its grid-service coverage and power-balance discussion contain explicit assumptions. The associated November 13 thread estimates 2.4 GW of IT by year-end across multiple buildings; neither forecast nor satellite-based count is verified operating capacity. SemiAnalysis →

Power and Battery Storage

Our analysis: batteries shift electricity through time. They can support peaks, outages and turbine scheduling, but cannot permanently fill a continuous energy deficit without adequate charging supply. Evaluate usable MWh, discharge MW, losses, reserve requirements, turbine derating and facility overhead together. No independent power balance is established here. Tesla’s possible commercial exposure is not quantified from a satellite count.

Next Observable Evidence

Verify each building’s power and customer acceptance; reconcile permanent generation commissioning with temporary-turbine retirement dates and grid energization.

Research Limits

Current net generation, firm grid delivery, battery commissioning and discharge capability, building-specific IT acceptance, customer allocation, financing terms and site earnings remain unresolved.

The year-end capacity and battery figures remain attributed estimates. A permit is not commissioning; a requested utility service is not energized firm delivery. No current aggregate operating MW is assigned, and this record is excluded from accepted-capacity aggregation.

Related Research

Stargate Abilene distinguishes customer-reported delivery from its planned campus envelope. Infrastructure Behind the Race to Superintelligence examines disclosed model-training and customer relationships.

AI-assisted public-source research; no interviews, site visits or independent operating-load measurements.

Company investor information & quarterly statements

Financial-disclosure review remains incomplete for one or more participants. The company-level limitations below remain unresolved; this section does not establish full corporate-disclosure verification.

Corporate disclosures provide company-wide context. They do not establish this project’s revenue, spending, profit, ownership share or operating capacity. Disclosure verification records →