SpaceX Cochise: Arizona’s Proposed Supercomputer Campus
Proposed · County review pending
Published November 6, 2026 · Evidence updated November 8, 2026
1.5 GW initial-phase electrical demand; up to 6 GW full-build plan across nine roughly 493,000-square-foot computing buildings. Neither is verified operating IT capacity.
Evidence · Compare · Milestones
Investment takeaway
SpaceX’s proposed Cochise County campus puts local tax relief at the center of a large AI infrastructure proposal. The application forecasts substantial revenue, while utility documents describe a phased power buildout that remains conditional. The investment question is whether approvals, contracts and taxable construction turn those projections into durable benefits. No operating IT capacity, project revenue or closed financing is established by this review.
A proposed campus near Apache Station
Tombstone Resources LLC seeks Special Use Authorization SU26-22 for approximately 747 acres along US 191 near Apache Generating Station. The application describes up to nine roughly 493,000-square-foot computing buildings in four phases, plus cooling, electrical, battery-storage and support infrastructure. Cochise County identifies SpaceX as host of the November 4 applicant-hosted community meeting; that establishes involvement but does not resolve the campus’s complete ownership or financing structure. The county says applicant estimates remain unverified and no approval has been made. [1, 2, 5]
One campus, two power scopes
The application and utility documents describe approximately 1.5 GW of initial-phase electrical demand and up to 6 GW at full build-out. These are proposed electricity requirements, not verified operating IT loads. The proposed primary supply is grid-delivered; the application also describes natural-gas standby generation for critical services and battery storage, so it should not be read as a no-generation campus. AEPCO’s letter describes preliminary phase-one transmission feasibility with identified upgrades; later phases require additional studies and infrastructure. Delivery depends on agreements, resources, construction and approvals. [2, 3]
Tax benefits: claims and evidence
Source review: November 6, 2026. This comparison summarizes the research below; estimates and possible outcomes remain separate from verified tax savings.
| Benefit | Public claim | What the record establishes | Missing calculation and source |
|---|---|---|---|
| Annual property-tax revenue | $34–103 million annually, projected by the applicant. | A developer estimate, not an independently verified fiscal appraisal. | Assessed values, phase timing, exemptions and allocation among taxing jurisdictions. Application → |
| Household property-tax relief | A possible 20% reduction has been publicly suggested. | No uniform 20% reduction in complete household bills is established by the reviewed record. | A jurisdiction-by-jurisdiction fiscal model connecting receipts, adopted levies and household bills. Separate tax rates → |
| Construction sales taxes | Approximately $250 million one-time county benefit, projected by the applicant. | The headline is not established as money entirely available to the jail district. | Taxable purchases, exemptions, eligible district receipts and collection timing. Application → |
| Earlier end to the jail tax | Construction revenue could help repay jail debt sooner. | Published terms link the tax sunset to secured-debt repayment or July 1, 2043, whichever is earlier; no two-to-three-year payoff is demonstrated. | Debt and repayment terms reconciled with eligible project receipts. Jail-tax terms → |
What the tax promise establishes
The applicant forecasts $34 million to $103 million in additional annual property-tax revenue and a one-time county sales-tax benefit of approximately $250 million. These are developer projections. The reviewed filing does not provide a fiscal worksheet establishing assessed values, exemptions, revenue allocation by taxing jurisdiction or a uniform 20% reduction in household tax bills. The quoted public claim is a possible outcome, not an adopted tax cut. [2, 4]
County relief and the household bill
Cochise County’s 2026 general-government rate is $2.6283 per $100 of assessed value. College, school, municipal and other district taxes are determined separately. For illustration, $30,000 of assessed value produces $788.49 in county general-government tax; a hypothetical 20% reduction saves $157.70. This is arithmetic using the current rate, not a project forecast, and does not reduce every component of a household bill by 20%. [6]
The expenditure-limit distinction
Arizona’s Auditor General describes a levy-reduction penalty after an unauthorized expenditure-limit violation and hearing. That is different from automatically rebating every dollar of new revenue. The legal mechanism alone does not establish the supervisor’s 20% estimate; a county finance analysis is needed to connect projected receipts, spending limits and adopted levies. [7]
Could construction taxes retire the jail debt?
The county’s published financing plan contemplated approximately $100 million in borrowing and encourages early repayment. The half-cent jail tax ends within 90 days after the secured debt is repaid, or by July 1, 2043. That supplies a mechanism for earlier tax termination. It does not demonstrate a payoff within two or three years: the project’s taxable spending, exemptions, jail-district receipts, financing terms and collection schedule must first be reconciled. The $250 million headline cannot be assumed to be entirely available to the jail district. [2, 8]
Electricity benefits depend on the contract
SSVEC says no final energy agreement has been executed. Its FAQ discusses developer-funded upgrades, guarantees, minimum payments and protections if the project closes or consumes less electricity than planned. AEPCO’s large-load framework requires public regulatory review. The cited docket is a review framework, not evidence that this campus already has an approved contract. Rate credits, cooperative capital and community contributions are different benefits and should not be added as if each were immediate household cash savings. [3, 9]
Water, workforce and public costs still need a calculation
The applicant describes closed-loop dry cooling rather than cooling towers, estimates roughly 7–10 acre-feet of annual operating water use at full build-out, and proposes no new production well for industrial use. It also describes treated wastewater from the adjacent generating station or trucked water for non-potable needs. Those are applicant design and supply claims—not independently verified operating consumption—and they do not eliminate construction or initial cooling-loop-fill needs. The filing further forecasts roughly 5,500 peak construction jobs, about 1,000 permanent positions at full build-out, and approximately $3.6 billion of applicant-funded transmission and substation work. Those are forecasts, not commitments or completed investment. Its fire narrative nevertheless identifies county law-enforcement and emergency-coordination roles, with a response agreement still to be sought. A net fiscal analysis should compare receipts with incremental public costs. [2, 3]
The next observable evidence
The next scheduled county checkpoint is the December 9 hearing at 2 p.m. Arizona time. A decision and conditions would address land use, not certify delivered power or computing. Track final electricity agreements, financial guarantees, phase-specific utility delivery, tax-treatment documents and an independently reviewed fiscal model. Hardware suppliers, tenant contracts, paid construction spending and project earnings remain unverified. [1, 3, 9]
Project at a glance
- Location
- Near Apache Generating Station, Cochise County, Arizona
- Applicant
- Tombstone Resources LLC
- Status
- Proposed; special-use application pending county review. No approved campus or operating IT load established.
- Capacity
- 1.5 GW initial-phase electrical demand; up to 6 GW full-build plan across nine roughly 493,000-square-foot computing buildings. Neither is verified operating IT capacity.
- Water and cooling
- Applicant proposes closed-loop dry cooling and estimates 7–10 acre-feet of annual operating water use at full build-out; the claim remains unverified and construction-related water needs remain separate.
- Next checkpoint
- December 9, 2026, 2 p.m. Arizona time: scheduled Planning and Zoning Commission hearing on SU26-22; a hearing is not an approval or commissioning date.
- Map precision
- County identifies the campus near Apache Generating Station along US 191. No independently checked parcel centroid; no map pin assigned.
FJI source-qualified: four-document gate met, including project-specific government evidence. Qualification evidence and decisions →
Sources and claim boundaries
Applicant claims, county decisions, utility commitments and independent reporting have different evidentiary roles. County hosting does not independently validate the applicant’s projections.
-
Cochise County project review
County identifies SU26-22, applicant Tombstone Resources LLC, approximately 747 acres, up to nine computing buildings in four phases and 6 GW at full build-out. December 9 hearing is scheduled for 2 p.m. Arizona time. County has not independently verified applicant estimates or approved the project.
Current application status and public hearing · Checked November 6, 2026
-
Tombstone Resources application
Applicant projects $34–103 million annual property-tax revenue and a $250 million one-time county sales-tax benefit. It describes nine roughly 493,000-square-foot computing buildings, dry cooling, battery storage, approximately 1,500 MW in phase one and 6,000 MW at full build-out. The application also forecasts roughly 5,500 peak construction jobs, about 1,000 permanent jobs and approximately $3.6 billion of applicant-funded grid work. These are applicant projections; fiscal calculations, operating demand, water use, allocation by jurisdiction and 20% household savings are not substantiated in the reviewed filing.
Cover letter pp1–3; operational, site-plan and utility appendices · Checked November 8, 2026
-
SSVEC project FAQ
No energy agreement is finalized. Infrastructure costs, guarantees, minimum payments and community benefits depend on negotiated agreements and ACC approval. Phase 1 is 1.5 GW; later phases could reach 6 GW.
Agreement, phasing, early-exit and community-benefits questions · Checked November 6, 2026
-
KJZZ project reporting
Original local reporting describes the proposal, developer revenue forecasts and utility negotiations. Forecasts remain attributed rather than independently audited fiscal results.
November 3 report; developer tax projections and utility comments · Checked November 6, 2026
-
Cochise County SpaceX town hall notice
County identifies the November 4 event as a privately organized SpaceX town hall. This supports SpaceX involvement, not a verified legal ownership percentage, complete corporate structure or financing close.
November 4 notice · Checked November 6, 2026
-
Cochise County property-tax rates
County general-government rate is 2.6283 per $100 assessed value. College, school, municipal and other district rates are separate; county-rate relief is not equivalent to the same percentage cut in a complete household bill.
2026 county, college and school rate tables · Checked November 6, 2026
-
Arizona Auditor General county expenditure limits
Unauthorized excess expenditures can trigger a reduction in the allowable primary property-tax levy after an Auditor General hearing. Receiving new revenue alone is not the stated trigger.
FAQ 4: penalty for exceeding expenditure limitation · Checked November 6, 2026
-
Cochise County jail financing
Published plan anticipates roughly $100 million in borrowing and permits early repayment. Tax ends within 90 days after secured debt repayment or by July 1, 2043. These provisions do not establish a two-to-three-year payoff from this project.
Tax termination; projected bond financing and early repayment · Checked November 6, 2026
-
AEPCO large-load agreement framework
Framework requires customer-funded upgrades, guarantees, cost accounting and ACC review of contracts and benefits. Docket E-01773A-26-0123 describes a review framework, not proof of an approved campus-specific contract.
Rural Cooperative Electric Service Agreement public briefing · Checked November 6, 2026
AI-assisted public-source research by Fjord Journal. No interviews, site visit, independent metering or whole-project certification. Source review does not verify tax savings, financing or commissioning.
Related analysis: SpaceX’s Arizona Data Center Puts a Tax Windfall to the Test
Company investor information & quarterly statements
Financial-disclosure review remains incomplete for one or more participants. The company-level limitations below remain unresolved; this section does not establish full corporate-disclosure verification.
Tombstone Resources LLC / SpaceX: No public quarterly financial statements have been reviewed. Current ownership and private-company status still need verification; no listed-parent exposure is assumed.
SSVEC / AEPCO: No public quarterly financial statements have been reviewed. Current ownership and private-company status still need verification; no listed-parent exposure is assumed.
Corporate disclosures provide company-wide context. They do not establish this project’s revenue, spending, profit, ownership share or operating capacity. Disclosure verification records →