Prime Storage Powers Ferry Place Data Center
Marietta approved conditional rezoning on August 12, 2026. Construction and commissioning remain unverified.
Project stage Approved / pre-construction
What the record establishes
- Current stage
- Approved / pre-construction
- Reported proposal
- 18 MW
- Zoning case
- Z2026-12
- Accepted IT load
- Unverified
Primary documents
Investment takeaway
The conversion cleared conditional rezoning before Marietta extended its pause on new applications. Construction, utility service and compliance with project conditions remain delivery milestones.
Project at a glance
- Location
- 1155 Powers Ferry Place, Marietta, Georgia
- Applicant
- Prime Storage Powers Ferry Place Marietta LLC
- Scope
- Partial conversion of an existing self-storage building
- Map precision
- Representative Marietta-area map pin. The city zoning record supplies the project address.
FJI source-qualified: four-document gate met, including project-specific government evidence. Qualification evidence and decisions →
What Marietta approved
On August 12 the council voted 5–2 to allow a data infrastructure use at 1155 Powers Ferry Place while retaining Community Retail Commercial zoning. The approval sets maximum noise levels of 56 dBA and 77 dBc, including in emergencies, and requires an independent acoustical study.
The citywide moratorium
The Powers Ferry application predates the original pause. On November 12 the council shelved a citywide zoning amendment and extended the pause on accepting new data center rezoning and permit applications through December 31, 2027. The August approval remains the documented site-specific milestone.
What remains unverified
Construction start, delivered power, accepted IT load, tenant, financing and operating dates remain unverified. The reported 18 MW describes the proposal.
Next evidence checkpoint
Verify building permits, construction start, utility service and compliance with zoning conditions.
Sources and claim boundaries
- Marietta City Council · 2026-08-12
City summary, Z2026-12. Approval included site-specific conditions and maximum noise levels of 56 dBA and 77 dBc.
- Marietta Planning Commission · 2026-07-01
Item 20260577 identifies the applicant, address, parcel and requested use.
- Marietta City Council · 2026-11-12
City summary, CA2026-06. Council tabled the proposed zoning amendment and paused new applications through December 31, 2027.
- FOX 5 Atlanta · 2026-08-12
Council voted 5–2. The application predated the original moratorium.
- Inside Self-Storage · 2026-08-14
Trade reporting describes a proposed 18 MW conversion.
AI-assisted public-source research by Fjord Journal. This review used public documents and included no site inspection or independent metering.
Company investor information & quarterly statements
Financial-disclosure review remains incomplete for one or more participants. The company-level limitations below remain unresolved; this section does not establish full corporate-disclosure verification.
Prime Storage Powers Ferry Place Marietta LLC
The Marietta zoning packet identifies the local LLC as the applicant and the property survey identifies it as owner.
The fund holding the LLC, tenant and construction financing remain unverified.
Prime Group Holdings
The firm describes itself as a private-equity real estate manager and publishes fund-level fundraising announcements.
Available fund disclosures leave the Marietta project allocation open.
Corporate disclosures provide company-wide context. They do not establish this project’s revenue, spending, profit, ownership share or operating capacity. Disclosure verification records →