Georgia · Proposed / development

Nixon Technology Center

Project stage Proposed / development

Augusta’s Planning Commission has scheduled a November 23 hearing on rezoning and a special exception. Georgia’s regional review is complete.

Published and sources reviewed November 22, 2026.

Investment takeaway

The campus’s proposed schedule depends on how 3 G Investments would power the first buildings. A draft fiscal analysis assumes on-site generation beginning in 2029 and permanent Georgia Power service in the second quarter of 2031. The next evidence to look for is a permitted interim generation plan and a signed utility agreement with phased delivery dates.

Project at a Glance

Location
South Augusta, Georgia
Project stage
Proposed / development
Capacity scope
600 MW estimated peak connected electrical load at build-out. IT load, contracted utility capacity and energization are unverified.
Named participants
3 G Investments, LLC; The Nixon Trusts; Georgia Power (named supplier)

FJI source-qualified: four-document gate met, including project-specific government evidence. Qualification evidence and decisions →

FJ Intelligence · Compare this project · Track milestones

What the applications cover

The city hearing agenda covers approximately 383 acres at Four H Club Road and Mike Padgett Highway. The state filing describes about 388 acres and 3.34 million square feet. Local reporting describes seven data center buildings. The state form gives 2028 and 2029 as estimated phase completion dates, with overall completion estimated for 2029.

The power plan

The state filing names Georgia Power and records a request for a study of existing transmission and distribution capacity. It describes possible backup turbines and battery storage. The draft MuniCap fiscal analysis, as reported by WRDW, separately assumes regular on-site generation starting in 2029 before permanent utility service in Q2 2031. The public record reviewed leaves the generation design, air permits, utility upgrades, cost allocation and service agreement open.

Project economics

The state filing estimates $3 billion of value at build-out and $38.8 million in annual local tax revenue. These are projections. WRDW reports that MuniCap’s model assumes $15 billion in tenant hardware while identifying no end user. The state filing estimates 40 full-time jobs and the draft model projects about 571 direct full-time equivalents. The basis for the difference remains unresolved.

Cooling and local review

The filing names Augusta Utilities and proposes closed-loop cooling. It gives no volume for the initial fill. Augusta’s planning director told WRDW that studies on noise, water and electricity are required at site-development application.

What remains unverified

A local zoning decision, site-development permits, a permitted and funded interim power plan, executed utility service, an anchor tenant, construction financing and accepted IT capacity remain unverified. The available record does not specify an AI tenant or workload.

Next evidence checkpoint

November 23, 2026, 2 p.m. ET: Augusta-Richmond County Planning Commission hearing on Z-26-18 and SE-26-22. Watch for its recommendation and subsequent action by the Augusta Commission. The state’s register logs a regional finding dated November 18.

Company disclosures

Southern Company owns Georgia Power. Its investor relations materials and third-quarter 2026 results provide company-level context. The reviewed materials establish no project-specific service commitment or revenue.

Sources

  1. Augusta Planning Commission special-called meeting agenda

    The November 23 agenda lists rezoning and a special exception covering about 383 acres.

  2. Georgia DCA regional review status

    The regional review is marked complete and the regional finding is dated November 18.

  3. Georgia DCA initial DRI filing

    The city hearing agenda covers approximately 383 acres at Four H Club Road and Mike Padgett Highway. The state filing describes about 388 acres and 3.34 million square feet.

  4. Georgia DCA additional DRI filing

    The filing estimates 600 MW peak connected demand, identifies Georgia Power and lists a $3 billion estimated build-out value.

  5. WRDW reporting on the draft fiscal analysis and local hearing

    Reporting on the draft MuniCap model describes bridge power starting in 2029 and permanent service assumed for Q2 2031.

  6. WRDW reporting on the required studies

    Noise, water and power studies are required at the site-development application stage.

By Fjord Journal

Company investor information & quarterly statements

Financial-disclosure review remains incomplete for one or more participants. The company-level limitations below remain unresolved; this section does not establish full corporate-disclosure verification.

3 G Investments / The Nixon Trusts

Augusta names 3 G Investments as the zoning applicant acting for The Nixon Trusts.

Campus financing and the eventual tenant remain undisclosed.

Supporting document

Southern Company / Georgia Power

The regional filing names Georgia Power as a potential supplier. Southern Company and Georgia Power file a combined Form 10-Q. An executed campus power agreement remains unverified.

Official investor & shareholder information · Quarterly financial statements: Q3 2026, quarter ended September 30, 2026

Corporate disclosures provide company-wide context. They do not establish this project’s revenue, spending, profit, ownership share or operating capacity. Disclosure verification records →