Project directory / Canada / Ontario
Microsoft YTO40 / 48 Lowe’s Place, Etobicoke
Under construction / installation and testing; Microsoft explicitly says the Etobicoke facility is not operational.
Sources reviewed November 14, 2026.
Compare · Track milestones · FJI evidence · Microsoft company research
Investment takeaway
YTO40 shows why contractual substantial performance and revenue-ready cloud capacity must be tracked separately. A Phase 1 improvement reached a contractual milestone in October 2026, while Microsoft still describes equipment installation and testing through fall 2027. No site revenue, utilization or return is established.
Project at a Glance
- Location
- 48 Lowe’s Place, Etobicoke, Toronto, Ontario, Canada
- Stage
- Under construction
- Capacity
- IT MW and contracted utility MW unverified. Historical building-area plans and a construction certificate do not establish delivered computing capacity.
- Company roles
- Microsoft; 3288212 Nova Scotia Limited (named project owner); EllisDon (contractor)
- Project finance
- Unverified
FJI source-qualified: four-document gate met, including project-specific government evidence. Qualification evidence and decisions →
One Contract Milestone, Further Delivery Work
The published substantial-performance certificate identifies the Phase 1 improvement and its October 6 milestone. It covers site improvements, administration and two colo fit-outs, with shell space for three more. That scope does not certify occupancy, energization, accepted customer compute or the operation of the entire campus.
Microsoft’s current update explicitly says the facility is not operational. Its expectation of equipment installation, testing and preparation through fall 2027 is a forward-looking timeline, not evidence that the site will open on a particular date.
Identity and Duplicate Boundary
This record concerns Microsoft-linked YTO40 at 48 Lowe’s Place, owned in the construction certificate by 3288212 Nova Scotia Limited. Original independent reporting links that entity and address to Microsoft. It is distinct from the separately tracked Compass Etobicoke campus; the shared city name is not grounds to merge them.
Toronto’s Next Checkpoint
The July Council action requested a December 9–10 report-back on potential environmental, water, electricity and noise impacts. It did not announce operational acceptance or a commissioning date.
Sources and Claim Boundaries
Council adopted an impact-review request on July 29–30, 2026 for the data centre at 48 Lowe’s Place. Staff were asked to meet the applicant and councillor about environmental, water, electricity and noise impacts and report back at the December 9–10 meeting. This is an impact-review action, not an operating approval. City of Toronto →
Microsoft says its Etobicoke datacentre is not operational. Building completion is expected in fall 2026, with equipment installation, testing and preparation continuing through fall 2027. The page gives both May 2024 and November 21, 2024 as construction-start references; their scope is not reconciled here. Neither target establishes service acceptance. Microsoft →
The October 20 certificate names P.17857 YTO40 Phase 1 at 48 Lowes Place, owner 3288212 Nova Scotia Limited and contractor EllisDon. It records October 6 substantial performance for site works, administration and Colo 1–2 fit-outs plus shell space for Colos 3–5. This is contractual scope, not an occupancy, energization or operating certificate. Daily Commercial News / ConstructConnect →
March 2022 original reporting connects Microsoft, project entity 3288212 Nova Scotia Limited and 48 Lowe’s Place. It describes a proposed replacement technology building and administration/support building on a former Lowe’s site. Historical proposed floor area is not treated as final as-built scope or current operation. DatacenterDynamics →
Next Observable Evidence
Toronto requested an impact-review report-back at its December 9–10, 2026 Council meeting. Separately seek phase-specific occupancy, commissioning and utility/customer acceptance records; do not infer operation from contract substantial performance.
Research Limits
Accepted IT capacity, energized utility service, occupancy/commissioning, customer workload, site investment, financing and economics remain unverified. Microsoft’s two construction-start references remain unreconciled; fall 2027 is a preparation target, not a confirmed opening date.
Unknown MW and project capital remain unavailable, not zero. No national or company-wide investment envelope is allocated to this facility. AI-assisted public-source research; no interviews or private-document review.
Company investor information & quarterly statements
Financial-disclosure review remains incomplete for one or more participants. The company-level limitations below remain unresolved; this section does not establish full corporate-disclosure verification.
Corporate disclosures provide company-wide context. They do not establish this project’s revenue, spending, profit, ownership share or operating capacity. Disclosure verification records →