Expanded investment research / Prineville / Crook County, Oregon — representative locality pin

Meta Prineville: A large mature footprint needs phase-level productivity

FJI source-qualified: four-document gate met, including project-specific government evidence. Qualification evidence and decisions →

Project status: Operating campus; city reports 11 completed buildings in FY2024; current IT capacity and per-building commissioning unverified. Capacity scope: City FY2024 report: 11 completed buildings, approximately 5 million sq ft; 2024 facility electricity 1,728,291 MWh; current IT MW unknown. How we verify evidence.

← Back to project index

Compare this project → · Track its catalysts → · Evidence guide →

Research snapshot
Location
Prineville / Crook County, Oregon — representative locality pin
Readiness
Operating
Status
Operating campus; city reports 11 completed buildings in FY2024; current IT capacity and per-building commissioning unverified
Confirmed companies
Meta
Next milestone
Accepted building inventory, resource requirements and incremental computing benefits
Reviewed
October 6, 2026

Expanded analysis · Original disclosures linked below · CAD and USD preserved as labeled · Company statements attributed; interpretations labeled.

The one-minute investment takeaway

Our analysis: A large mature footprint needs phase-level productivity. Prineville adds Meta’s original custom-built campus area. Its historical expansion provides scale, but the operating and capital state of each building needs reconciliation.

Readiness basis: Classification of evidence in the reviewed profile; strongest documented phase, not full-campus completion. Operating campus; city reports 11 completed buildings in FY2024; current IT capacity and per-building commissioning unverified Readiness source →

What the sources establish

Who receives the money?

Our analysis of disclosed roles. Revenue routes are business-model interpretations, not estimates of booked project revenue.

Company / exposureEconomic roleWhat investors need to establish
MetaOwner or operator of the disclosed infrastructureAccepted useful capacity and net contribution after resource and renewal costs.
Named service and construction participantsContract-specific delivery and recurring service rolesActual contract, tariff or purchase terms; participation is not booked profit.
Equipment suppliers not established herePotential procurement and renewal spendingNamed awarded orders before attributing public-company project revenue.

How financially meaningful is it?

Our analysis: A multibuilding campus can offer economies in staffing, network and site services while concentrating resource and technology-renewal obligations. Separate buildings already delivering useful work from shells, prospective phases and later density upgrades. Meta’s 2021 square-foot envelope was described as a full-buildout expectation; it cannot be turned into current IT MW by an assumed density. The current budget headline is broadly consistent with the earlier envelope, but that does not establish actual money spent or phase acceptance. Energy matching and water restoration were discussed by the operator; they serve different roles from physical electricity delivery and water available at peak. The next refresh should be tested for useful output after server, thermal, electrical and maintenance costs. Neither original-campus status nor a longstanding local workforce guarantees the best incremental return within Meta’s portfolio.

How to test the economics

Computing contribution equals customer or product benefit minus power, network, facility operation, financing and equipment renewal. Model long-lived buildings separately from shorter-lived computing assets.

Hypothetical illustration: 10 MW steady IT load at 1.2 PUE uses 105,120 MWh annually. A USD 10/MWh tariff increase adds USD 1.0512 million annual cost. Neither load, PUE nor tariff is disclosed here; this is a sensitivity example, not a site forecast.

Milestones that would change the assessment

MilestoneEvidence to watch
Scope and capitalReconcile campus and portfolio figures, accepted versus potential capacity, and property versus equipment funding.
Electrical and cooling acceptanceCurrent accepted phases, reconciled capital scope and measured computing productivity. Equipment delivery, construction completion and commissioning are separate steps.
Commercial productivityUseful workloads or billable customer capacity, with operating costs and renewal obligations included.
Counterparty attributionNamed binding service and procurement terms before estimating participant earnings.

What could break the investment case?

Our analysis: Common infrastructure can become a bottleneck for multiple phases. Hardware obsolescence, resource obligations and retrofit costs may consume cash long after the first opening.

What would change our view?

Our analysis: Dated acceptance, improved useful output and competitive net resource costs would strengthen our assessment. Underutilized capacity, expensive upgrades without customer support, or rising renewal costs ahead of economic benefits would weaken it. We would update this profile using campus-specific operating and contractual evidence. A larger corporate investment headline, a grant program or a design capability alone would not establish a stronger return.

What remains unknown

Resolved historical construction count: city reports 11 completed buildings. Remaining: individual occupancy/IT commissioning dates, future expansion scope, current nameplate/peak and IT MW, hardware utilization, site earnings, tariff and phase capex. Annual facility electricity is disclosed for 2023–2024; it is not a current capacity or utilization measure.

Project research for information, not a buy recommendation. Financial illustrations use assumptions, not disclosed site results or management guidance.

Readiness evidence update · October 14, 2026

Operating existing campus. Meta’s current Prineville information sheet explicitly describes operational data-center buildings and operational jobs. A 2018 company newsroom account records the original campus opening in 2011. A city economic-opportunities analysis hosted by Oregon corroborates the established campus. These support existing-campus operation, not acceptance of every expansion.

This corrects our readiness classification; it does not report a new opening. Current accepted IT MW, utilization, site earnings and completion of all expansions remain unverified. No capacity or spending quantity is promoted into aggregate totals.

  • Meta Prineville information sheet

    The current fact sheet describes operational Prineville data-center buildings, operational jobs and utility/water-service arrangements. These support existing-campus operation, not a quantified energized IT load or complete building-acceptance inventory.

  • Meta newsroom

    The company states that its first custom-built Prineville data center opened in 2011. The same 2018 article discusses further proposed expansion; historical additions are not assumed completed today.

  • City of Hermiston economic opportunities analysis, Oregon-hosted

    The analysis identifies established Apple and Meta campuses in the Prineville area. This is regional planning context, not a Prineville operating permit, phase acceptance record or current MW measurement.

Capacity, utilization and expansion gap review · October 14, 2026

Construction scope narrowed

City management reports 11 completed buildings and approximately 5 million square feet in its FY2024 financial report. Fortis describes 4.6 million square feet delivered; the area boundaries differ and remain separately attributed. This replaces a blanket unknown about the historic 11-building program with dated completion evidence.

Actual annual facility energy

Meta reports 1,375,321 MWh in 2023 and 1,728,291 MWh in 2024. FJI derives a 2024 annual average facility draw of approximately 196.75 MW by dividing by 8,784 leap-year hours. This includes facility energy, not just computing, and is not current IT capacity, peak load or a utilization percentage.

Remaining questions

Resolved historical construction count: city reports 11 completed buildings. Remaining: individual occupancy/IT commissioning dates, future expansion scope, current nameplate/peak and IT MW, hardware utilization, site earnings, tariff and phase capex. Annual facility electricity is disclosed for 2023–2024; it is not a current capacity or utilization measure.

Additional source evidence

OPB / KLCC. The Business Oregon memorandum identifies Facebook Prineville tax-program facilities as of 2023. Incentive units are not a current campus building count, operating capacity or 2026 tax-status verification.

Company investor information & quarterly statements

Meta Platforms

Project participant recorded in reviewed project profile; consolidated corporate disclosure only

Official investor & shareholder information · Quarterly financial statements: 2026 Q2, quarter ended June 30, 2026

Corporate disclosures provide company-wide context. They do not establish this project’s revenue, spending, profit, ownership share or operating capacity. Disclosure verification records →

Company research: documented roles

Follow the company profile for financial context. The evidence supports the specific role described here.

Role evidence does not establish project revenue, ownership economics, accepted capacity or a percentage of company sales.