Israel · Beit Shemesh · FJ Intelligence Project Research

Mega DC Beit Shemesh (MDCIL-4)

Project stage Under Construction

Under construction. Nebius has contracted first-phase capacity, and the November agreement covers a further phase at Beit Shemesh alongside a separate Masmiya site.

FJ Intelligence Evidence

What the record establishes

58 MW of IT capacity under the January agreement at Beit Shemesh. The November agreement adds 134 MW of IT capacity across Beit Shemesh and Masmiya combined.

Evidence base
5 reviewed documents
Current stage
Under construction
January contract
58 MW IT at Beit Shemesh
November deal target
End of Q2 2028

Project at a glance

Location
Beit Shemesh, Israel
Developer
Mega DC, a Mega Or subsidiary
Customer
Nebius
Next checkpoint
First-phase handover and fit-out

FJI source-qualified: four-document gate met, including project-specific government evidence. Qualification evidence and decisions →

Investment takeaway

The staged Nebius agreements give Mega DC a named AI cloud customer before commissioning. The timing of revenue depends on handover and service commencement. Mega Or’s NIS 550 million forecast for annual net operating income covers both facilities in the November deal at full occupancy.

The Beit Shemesh campus

Beit Shemesh Municipality publicly discussed the project in December 2025. Mega Or’s first-quarter 2026 filing identifies MDCIL-4 in the North Beit Shemesh industrial area and lists its first two phases under construction. The map uses a representative city point.

What Nebius has contracted

58 MW of IT capacity under the January agreement at Beit Shemesh. The November agreement adds 134 MW of IT capacity across Beit Shemesh and Masmiya combined. Trade reporting says the second Beit Shemesh phase has grid connection approval. The Masmiya facility, MDCIL-7, is a separate site and still needs grid approval.

Capacity and delivery

Mega DC lists 240 MW of total campus power. The developer’s total-power figure and the contract’s IT-capacity figures measure different things. The issuer’s Q1 phase estimates are a dated design snapshot. First-phase fit-out expected in Q4 2026, according to November reporting. End of Q2 2028 is the reported target for the two facilities in the November deal.

What remains unverified

First-phase handover, live IT load, project-level capital and returns, utility service terms and a precise site pin remain unverified. The Masmiya grid approval remains a condition for that site.

Next evidence checkpoint

Confirm first-phase handover and fit-out, then verify energized IT capacity and the capacity allocation for the second phase.

Investor Disclosures

Nebius investor information · Nebius Q3 2026 shareholder letter · Mega Or Q1 2026 interim financial report. These documents cover company results. Campus-level returns remain unverified.

Related Coverage

Nebius / Mega DC Modi’in · Nebius company research

Sources and Claim Boundaries

  1. Beit Shemesh Municipality

    City officials describe Mega Or’s proposed AI data center in Beit Shemesh following a project briefing. The notice does not establish grid authorization, construction milestones or a capacity measurement basis.

  2. Mega Or Q1 2026 interim report

    The issuer lists MDCIL-4 phases A and B under construction at 60 MW IT each in its Q1 snapshot. Phase C appears separately under land for future development.

  3. Mega DC site portfolio

    The developer lists MDCIL-4 as its Beit Shemesh campus and gives 240 MW under total power. Its current site table cites 120 MW under construction and 60 MW ready for service in 2027. These figures are presented on the operator’s stated basis.

  4. CTech / Calcalist

    Reports 58 MW IT at Beit Shemesh in the January deal, a November agreement spanning 134 MW IT across two sites, and grid connection approval for the Beit Shemesh facility. Reports a Q2 2028 target for the two facilities.

  5. Nebius Q3 2026 shareholder letter

    Nebius says additional Israeli colocation phases were scheduled for Q4. The letter does not identify those phases by site.

Reviewed November 23, 2026. Source-qualified. Whole-project certification and corporate disclosure review remain open.