Project directory / Greensparc Cordova Hydro Edge Pilot
Greensparc Cordova Hydro Edge Pilot
Project stage Pilot deployed
Investment takeaway
Cordova provides evidence of a deployed edge installation using a remote microgrid. Its repeatability depends on aligning flexible computing demand with surplus hydro and limiting winter backup costs.
- Location
- Humpback Creek hydroelectric facility near Cordova, Alaska
- Stage
- Pilot deployed
- Status
- A modular computing pilot was deployed at Humpback Creek. Current uptime and paid utilization remain unverified.
- Capacity
- 150 kW cited by Greensparc and UAF. NLR reports 170 kW of delivered computing capacity; the measures are not reconciled.
- Participants
- Greensparc and Cordova Electric Cooperative
- Next milestone
- Document winter uptime, hydro and diesel shares, metered power use and paid customer demand.
- Sources reviewed
- November 21, 2026
FJI qualification held or pending: the full four-document gate, including project-specific government evidence, has not yet been accepted. Qualification evidence and decisions →
Power and weather
The pilot sits inside the run-of-river plant, where cold mountain water can assist cooling. The cooperative expects some winter diesel use when river levels drop. Published sources do not establish a year-round hydro-only fuel mix or a measured PUE.
Customers and capacity
The national lab describes computing for utility controls and local businesses, together with a trial of GPU-as-a-service. The 150 kW and 170 kW reports may use different measurement scopes. Neither establishes contracted customer capacity or paid utilization.
Project economics
Surplus hydro can supply otherwise unused generation. Winter diesel, connectivity, equipment and maintenance costs determine delivered compute economics; project revenue is undisclosed.
What remains unverified
Current continuous operating status, metered winter fuel mix, actual uptime, realized PUE, customer terms and utilization remain unverified.
Sources
- National Laboratory of the Rockies
Describes the deployment, 170 kW computing figure, local uses, surplus hydro and expected winter diesel use.
- Greensparc
Operator reports a 150 kW modular deployment with Cordova Electric Cooperative.
- University of Alaska Fairbanks / ACEP
Corroborates installation, 150 kW figure and local microgrid context.
- Data Center Dynamics
Independent reporting on equipment delivery to Humpback Creek and HPE participation.
By Fjord Journal · AI-assisted reporting and analysis
Company investor information & quarterly statements
Financial-disclosure review remains incomplete for one or more participants. The company-level limitations below remain unresolved; this section does not establish full corporate-disclosure verification.
Cordova Electric Cooperative
The cooperative confirms member ownership and governance.
Project-specific financial performance remains undisclosed.
Greensparc
Greensparc identifies itself as the cooperative’s technology partner for the 150 kW modular pilot.
Greensparc’s ultimate ownership and the pilot’s paid utilization remain unverified.
Corporate disclosures provide company-wide context. They do not establish this project’s revenue, spending, profit, ownership share or operating capacity. Disclosure verification records →