Expanded investment research / Waltham Cross, Hertfordshire, United Kingdom

Google Waltham Cross

FJI source-qualified: four-document gate met, including project-specific government evidence. Qualification evidence and decisions →

Project status: Google reports the data centre open; capacity and utilization undisclosed. Capacity scope: Part of a two-year £5 billion U.K. investment; campus capacity not disclosed. How we verify evidence.

Project and ownership

Alphabet / Google. One named campus or explicitly bounded multi-campus development; reported envelopes are not operating IT load.

Power, permits and delivery

Google reports the data centre open; capacity and utilization undisclosed

Financing and economics

Google includes the campus in a wider £5 billion U.K. investment program; site-level allocation and earnings are undisclosed.

Investor implications · Our analysis

Public-record evidence narrows development uncertainty but does not establish utilized compute, billable capacity, attributable earnings or a stock recommendation.

What to watch next

Verify campus capacity, operating load and expansion approvals

Risks and unknowns

IT capacity, utility load, utilization, campus-level investment and expansion schedule remain undisclosed.

Sources and verification

Four project-specific sources reviewed, including at least one public-agency record.

  1. Company location disclosureGoogle

    Google identifies Waltham Cross as an operating data-centre location.

  2. Company opening disclosureGoogle

    Google announced opening the campus as part of a two-year £5 billion U.K. investment.

  3. Local government recordBorough of Broxbourne

    Broxbourne council records refer to planning permission for the Google data centre in September 2023.

  4. Independent specialist reportingDatacenterDynamics

    DCD independently reported opening and noted that capacity was not disclosed.

Reviewed October 7, 2026 · Source audit

Company investor information & quarterly statements

Alphabet

Google campus operator; regional UK commitment not site budget.

Official investor & shareholder information · Quarterly financial statements: 2026 Q2, quarter ended June 30, 2026

Corporate disclosures provide company-wide context. They do not establish this project’s revenue, spending, profit, ownership share or operating capacity. Disclosure verification records →

Scoped FJI evidence check · October 16, 2026

Target: Planning September 2023, construction start January 2024; no original dated RFS target established.

Dated evidence: Opening announced September 16, 2025; no metered IT MW established.

Still open: Site-specific cost and operating IT MW unavailable in read sources. UK energy-management agreement not site-only electricity volume.

Sources: Google · Borough of Broxbourne · DatacenterDynamics

Field-level review; original whole-profile dates and readiness classification retained. FJ Intelligence record →

Company research: documented roles

Follow the company profile for financial context. The evidence supports the specific role described here.

Role evidence does not establish project revenue, ownership economics, accepted capacity or a percentage of company sales.