Project research / United States / Alaska

DeepGreen Cook Inlet Subsea Compute

Project stage Feasibility permit application

Investment takeaway

The Cook Inlet proposal would pair tidal generation with subsea computing. The commercial test is whether usable power and service windows can support customer workloads through winter and across the tidal cycle.

Research snapshot
Location
East Foreland corridor near Nikiski, Alaska
Stage
Feasibility permit application
Status
FERC accepted a preliminary permit application for filing under P-15423. A permit decision and a construction license were not verified.
Capacity
About 100 MW of proposed tidal generation in the FERC notice. Firm IT capacity is unverified.
Participants
DeepGreen Cook Inlet SPV, LLC
Next milestone
FERC decision on P-15423, followed by year-round resource, equipment and environmental evidence.
Sources reviewed
November 21, 2026

FJI qualification held or pending: the full four-document gate, including project-specific government evidence, has not yet been accepted. Qualification evidence and decisions →

FJ Intelligence · Compare this project · Track milestones

Power and cooling

The filing proposes roughly 330–350 turbines and 66 modular compute pods, with passive subsea cooling and a hybrid power and fiber cable to Nikiski. Seasonal ice, suspended sediment and turbulence make maintenance frequency and vessel access material to uptime.

Permitting and local concerns

A preliminary permit would confer filing priority during the permit term. A construction license would require further review. Local reporting documents fishing-industry concerns and participation by the Kenai Peninsula Borough. This docket covers Cook Inlet, separate from DeepGreen’s Western Passage proposal.

Project economics

The cost of subsea installation, retrieval and maintenance, backup power, and lost compute time would determine delivered economics. No financed capital budget or customer agreement was verified.

What remains unverified

Permit decision, winter performance and maintenance evidence, firm IT load, grid or backup power terms, environmental approvals, financing and customer commitments remain open.

Sources

  1. FERC / Federal Register

    Acceptance for filing, project scope, proposed equipment and preliminary permit purpose.

  2. FERC eLibrary

    Separate Cook Inlet docket and applicant identity.

  3. National Renewable Energy Laboratory

    Cook Inlet tidal resource, seasonal ice and suspended sediment. Regional evidence rather than a project field test.

  4. Renewable Energy

    Measured currents and turbulence at East Foreland during a summer resource campaign.

  5. National Fisherman

    Reports local fishing concerns and Kenai Peninsula Borough intervention.

  6. Alaska’s News Source

    Independent reporting on proposed scope and local environmental concerns.

By Fjord Journal · AI-assisted reporting and analysis

Company investor information & quarterly statements

Financial-disclosure review remains incomplete for one or more participants. The company-level limitations below remain unresolved; this section does not establish full corporate-disclosure verification.

DeepGreen Cook Inlet SPV LLC

FERC names the LLC as the applicant seeking a preliminary permit to study feasibility under P-15423.

Ultimate ownership, committed financing and commercial counterparties remain unverified.

Supporting document

Corporate disclosures provide company-wide context. They do not establish this project’s revenue, spending, profit, ownership share or operating capacity. Disclosure verification records →