Europe · Germany

Colt DCS Berlin 1 & 2 · BER01/02

Project stage Planning

Investment takeaway

The substation is the first documented construction milestone. Delivery depends on energization, permits and construction of the first data hall.

Research snapshot
Location
East of Berlin, Brandenburg, Germany
Identifier
BER01/02
Status
Construction started on the 110 kV substation. Colt said the data halls remain in planning.
Capacity
Colt reports an 80 MVA power contract and a combined 54 MW of planned IT capacity across both halls.
Participants
Colt Data Centre Services; H&MV Engineering
Sources reviewed
November 22, 2026

FJI qualification held or pending: the full four-document gate, including project-specific government evidence, has not yet been accepted. Qualification evidence and decisions →

FJ Intelligence · Compare · Track milestones · Deutsch

What the records establish

Berlin’s government directory lists Colt DCS BER01/02 in Brandenburg. Colt describes a 9.5-acre site east of Berlin. H&MV Engineering is delivering the gas-insulated substation. The 80 MVA contract is an electrical supply rating. Colt’s 54 MW figure covers planned IT load across both halls, with the end-2028 service target applying to Berlin 1.

What remains unverified

The exact municipality, data-hall permits, energization date, customers and contracted workloads remain unverified.

Next milestone

Verify site-specific hall permits and substation energization before the Berlin 1 service target.

Sources

  1. Berlin Senate economic administration
  2. Colt DCS Berlin 1 and 2
  3. Colt DCS German expansion announcement
  4. Data Center Dynamics

Company investor information & quarterly statements

Financial-disclosure review remains incomplete for one or more participants. The company-level limitations below remain unresolved; this section does not establish full corporate-disclosure verification.

Colt Data Centre Services

Colt identifies Colt Group Holdings Limited as its parent.

The Berlin project financing and campus-level accounts remain undisclosed.

Supporting document

H&MV Engineering

H&MV is linked to the Berlin substation work. Exponent disclosed an approximately €750 million continuation vehicle for its H&MV investment in August 2026.

The vehicle figure covers Exponent’s investment arrangement. The Berlin contract value remains undisclosed.

Supporting document

Corporate disclosures provide company-wide context. They do not establish this project’s revenue, spending, profit, ownership share or operating capacity. Disclosure verification records →