Project directory / Iceland
Borealis Blönduós AI Campus Expansion
Project stage Under construction
Published and evidence reviewed November 16, 2026.
New 7,600 m² expansion building under construction; additional 12 MW long-term power agreement signed; interior technical systems work underway; completion and commissioning unverified.
FJ Intelligence evidence · Compare projects · Track milestones
Investment takeaway
Borealis Blönduós is a documented construction-stage AI-infrastructure expansion, not yet a disclosed revenue or return stream. The investor question is whether the new building and contracted power convert into commissioned, utilized capacity with observable customers and economics.
What is under construction
Ístak reports a new 7,600-square-metre data-center building, groundworks beginning in May 2026, interior piping and electrical work underway, and switchgear and backup-power works in progress. Municipal records separately document a construction camp and a separated fiber route at the Fálkagerði site.
Power is contracted, not commissioned
Landsvirkjun announced 12 MW of additional firm power under a long-term agreement. That is material evidence of supply preparation, but it is not commissioned IT load, full-building capacity or proof of customer utilization.
The 100+ MW claim needs discipline
Borealis markets more than 100 MW of campus expansion capacity. Fjord Journal treats that as an operator design and marketing claim for the wider campus, not as delivered, energized or operating capacity for this 2026 expansion.
Ownership and financing
Vauban Infrastructure Partners says its Core Infrastructure Fund III owns 92.2% of Borealis. Its approximately $148 million financing announcement concerns company-level facilities and cannot be allocated to this project. Borealis and the project remain private, with no public quarterly project accounts.
What is still unknown
No reviewed source provides the expansion's budget, paid capital, named customers, contracted revenue, utilization, GPU count, commissioned IT load, completion date or expected return. Those remain the material gaps for investors.
What to watch next
The next decisive evidence is building completion, phase-specific energization, customer acceptance and commissioned IT load. Project-level spending, revenue and utilization would then allow a more meaningful investor assessment.
Research limits
The record qualifies a bounded expansion profile and its current construction stage. It does not certify the whole campus, operating performance, project economics or future delivery.
Project at a glance
- Location
- Fálkagerði 1–11, Blönduós, Húnabyggð, Iceland
- Stage
- Under construction
- Capacity scope
- 7,600 m² expansion building; 12 MW additional contracted power. Borealis advertises 100+ MW of campus expansion capacity, not verified as delivered or as IT load.
- Timing
- Groundworks began in May 2026; interior piping and electrical work was underway by November 10, 2026; completion date unavailable.
- Map precision
- Community-mapped Borealis campus locator at Fálkagerði, not an official parcel point or the boundary of the 2026 expansion building. Municipal records independently support the Fálkagerði 1–11 site.
FJI source-qualified: four-document gate met, including project-specific government evidence. Qualification evidence and decisions →
Sources and claim boundaries
- Húnabyggð Municipal Council
The municipal council accepted Borealis's request to work toward a letter of intent for continued development and expansion of its Blönduós data center. This establishes municipal engagement, not a completed land or financing agreement.
agenda item 10; lines 540–542 · Document date: 2026-05-12 · Read November 16, 2026.
- Húnabyggð Planning and Transport Committee
The committee approved Ístak's temporary construction camp at Fálkagerði 1–11 and a separated Míla fiber route to the Borealis data center. A related planning amendment covering the site and new lots was deferred, so approval of the whole expansion plan is not inferred.
agenda items 4 and 8; lines 261–269 and 290–301 · Document date: 2026-09-01 · Read November 16, 2026.
- Landsvirkjun
Landsvirkjun announced a long-term agreement for 12 MW of additional firm electricity for Borealis's Blönduós expansion and described liquid-cooled NVIDIA equipment and AI services. Contracted power is not treated as energized IT load or full-building capacity.
official announcement; retrieved result text · Document date: 2026-06-23 · Read November 16, 2026.
- Ístak
Ístak reported a new 7,600-square-metre data-center building, groundworks beginning in May 2026, interior piping and electrical work underway, and switchgear/backup-power works in progress. It did not provide a completion or commissioning date.
lines 8–21 · Document date: 2026-11-10 · Read November 16, 2026.
- Borealis Data Center
Borealis described the agreement as enabling the next Blönduós expansion phase for AI and high-performance computing with next-generation NVIDIA infrastructure. The announcement calls the program a major investment but gives no project amount, customer, revenue or return data.
lines 6–81 · Document date: 2026-07-23 · Read November 16, 2026.
- RÚV
RÚV independently reported data-center investment activity and showed construction at the Borealis Blönduós site. It does not establish the expansion's budget, commissioned capacity, utilization or project cash flow.
article and construction photograph dated September 3, 2026 · Document date: 2026-10-28 · Read November 16, 2026.
- Vauban Infrastructure Partners
Vauban said its Core Infrastructure Fund III owned 92.2% of Borealis and announced approximately $148 million of company-level debt facilities. The financing is not attributed to the Blönduós expansion and does not establish project spending.
official press release · Document date: 2025-02-06 · Read November 16, 2026.
- Borealis Data Center
Borealis markets the operating Blönduós campus with 100+ MW of expansion capacity and PUE as low as 1.03. These are operator design/marketing claims, not evidence that the 2026 expansion is delivered, energized or operating at that scale.
lines 11–48 · Document date: Undated current page · Read November 16, 2026.
AI-assisted public-source research by Fjord Journal. No site visit, private contract review or independent metering. Contracted power, campus expansion capacity and company-level financing are excluded from operating-capacity, project-spending, revenue and return aggregates.
Company investor information & quarterly statements
Borealis Data Center: No public quarterly statements or project-level financial disclosure; company-level financing is not project spending.
Official ownership / investor evidence
Private disclosure evidence checked 2026-11-16. No public quarterly statement is substituted or invented.
Vauban Infrastructure Partners: Private ownership exception; approximately $148 million financing is company-level and not allocated to this expansion.
Official ownership / investor evidence
Private disclosure evidence checked 2026-11-16. No public quarterly statement is substituted or invented.
Corporate disclosures provide company-wide context. They do not establish this project’s revenue, spending, profit, ownership share or operating capacity. Disclosure verification records →