Project Directory / Georgia
Amazon ATL068 / ATL078 Lithia Springs
Project stage Proposed / development
Current status: Georgia's issued-permit register lists the shared backup-generator permit; construction progress, utility delivery and commercial operation remain unverified.
Published and sources reviewed November 19, 2026. Historical permit and agreement dates remain labeled.
Compare this project · Track milestones · FJI evidence
Investment takeaway
The permit record defines backup-equipment scope, not productive computing capacity. Investor relevance turns on dated construction, utility and customer-service evidence that can connect capital to usable AWS capacity.
Project at a Glance
- Location
- Lithia Springs, Douglas County, Georgia — facility-registry reference point
- Stage
- Proposed / development
- Capacity scope
- 188 emergency diesel generators across ATL068 and ATL078; no supported IT MW or accepted utility load established.
- Named parties
- Amazon / AMZN
FJI source-qualified: the four-document gate is met with project-specific government evidence and independent reporting. Corporate and whole-project certification remain separate.
What the Evidence Establishes
- Georgia EPD — issued-permit register. The current issued-permit register identifies permit 7374-097-0101-S-01-0 and the August 18, 2025 issuance date. The register page could not be rendered in the current source tool and the linked PDF available to review remained an unsigned draft; no signed-final-PDF claim is made. Source →
- Georgia EPD — July 2025 public advisory. Application 29644 names ATL068 and ATL078, both addresses and 188 emergency generators. It is a proposed-permit notice and does not itself establish final issuance or startup. Source →
- Georgia EPD — permit conditions. The accessible unsigned draft identifies 180 critical, six house, one boost-pump and one security emergency generator. Condition 7.1 requires notice within 15 days after startup. No startup notice was verified. Source →
- EPA ECHO — facility registry. Federal facility record supplies a registry reference point. It is not a surveyed campus boundary and does not establish construction or operation. Source →
- Data Center Record — ATL068/ATL078. Corroborates permit identity, issuance date and addresses from the state register. It does not establish utility delivery, commissioned IT capacity or commercial service. Source →
- Amazon — third-quarter 2026 results. Provides current AWS corporate context only. It does not allocate capital, capacity, revenue or a service date to ATL068 or ATL078. Source →
Final-permit read limit: The official issued-permit register identifies the permit and issuance date, but the directly readable linked PDF was an unsigned draft. Fjord Journal does not describe the signed final PDF as independently read.
Next Evidence
A startup notice, county construction/occupancy record, executed utility-service evidence or campus-specific commercial acceptance.
What Remains Unknown
Campus construction progress, utility service, contracted electrical load, commissioned IT capacity, startup notice, commercial service date, site capex and site earnings remain unverified.
AI-assisted public-source research. No original interviews, private contracts, site visits or independent operating measurements.
Company Investor Information & Quarterly Statements
Amazon company profile provides consolidated reporting context. No project revenue, cost, accepted load or share of AWS results is inferred.
Related Reporting
What 188 Backup Generators Tell Us About Amazon’s Lithia Springs Data Centers