HostDime SuperNova nears inspections; an opening remains unverified
New research published October 8, 2026 · historical milestones dated in profile · Sources reviewed: 2026-10-08
Published 2026-10-08. Historical events retain their source dates; this publication does not imply a new project milestone.
Final construction, commissioning and inspections described by operator; occupancy and opening unverified. Operator design: 100,000 sq ft and more than 1,000 racks; local 120,000 sq ft report unresolved; operating IT MW unknown.
Investor implications · Our analysis
WKMG reports a $100 million project cost, not verified incurred spending or a closed financing package. HostDime markets colocation and private-cloud services, but no contract revenue, leased-rack count, occupancy, debt terms or project margin is disclosed in reviewed documents. Duke Energy is a company-reported planning counterparty; DUK earnings cannot be estimated from that relationship. Our analysis: the economic inflection requires occupied, billable service after inspections and commissioning.
What to watch next
Dated final inspections, occupancy certificate, utility acceptance and customer-service start
Sources and verification
4 distinct accessible documents, including a project-specific government record and independent original reporting. Details and unresolved claims are preserved in the full profile and Florida source audit. Publication is new research, not a new project-status event.
- Town of Eatonville Council · 2026-09-01
Official council agenda includes discussion of HostDime’s previous development-agreement amendments and consideration of amendment 3, with agreement attachments. This verifies the town’s project record; an agenda does not establish adoption of proposed fines, occupancy authorization or operation.
- HostDime · Publication date not established
Operator describes SuperNova at 1 Innovative Pl as its seven-story 100,000-square-foot flagship, with more than 1,000-rack design capacity. It says final construction, commissioning and inspections continue, and describes Duke Energy coordination and closed-loop, air-cooled chilled-water cooling. These are company descriptions, not measured load, utility acceptance or independent Tier IV certification.
- WFTV / Dave Jordan · 2026-09-03
Independent local reporting quotes the CEO’s possible October opening conditional on final inspections after repeated delays. It reports prior $250-per-day fines. Its 120,000-square-foot figure differs from the operator’s 100,000; scope reconciliation remains open. The article does not establish passed inspections.
- WKMG / ClickOrlando, Mark Lehman · 2026-09-01
Reports the planned council consideration of $500-per-day penalties and additional site commitments, plus a reported $100 million project cost and municipal water/sewer reimbursements. URL says August 31, but visible publication/update date is September 1. Proposed accountability terms are not treated as adopted.
Page Update History
— Added publisher attribution, AI disclosure and this update-history section. This presentation update does not represent a new factual source review.
Earlier publication and source-review dates remain as stated on this page. This is the first entry in this standardized log; it is not a reconstruction of earlier revisions.